You are here

IN BRIEF

Nuclear Monitor Issue: 
#704
26/02/2010
Shorts

Germany: debate on n-power in CDU party.

Debate is still raging in the German government over the use of nuclear power. Chancellor Merkel has distanced herself from comments by environment minister Norbert Röttgen a day earlier. On February 20, Röttgen predicted that Germany would be free of nuclear power by 2030. By 2030, Germany's youngest nuclear power stations will have reached a lifespan of 40 years, eight longer than that agreed in 2000 on by former Chancellor Gerhard Schröder's centre-left coalition of Social Democrats and Greens. Röttgen, a member of the conservative Christian Democrats, told the Frankfurter Rundschau newspaper that even by the most skeptical of forecasts, Germany would reach its goal of getting 40 percent of its energy from renewable sources by 2030, thus allowing the country's remaining nuclear power stations to shut down. Renewable sources currently supply 16 percent of Germany's electricity. "In the coalition contract it says that nuclear power is a stopgap until renewable energy can take over the supply reliably and at competitive prices. That's exactly the line I am following." But the Federal Environment Agency (UBA) believes that this target is still achievable. "We can still cover 40 percent from renewable energy by around 2020," UBA president Jochen Flasbarth told the Süddeutsche Zeitung newspaper on the same day.  A few days later, on February 23, Peter Mueller, Christian Democratic prime minister in the German state of Saarland, said the government should stick to its timetable to phase out nuclear power. Amending the phase-out, fixed by legislation in 2002 for about 2021, “needs plausible grounds,” Mueller is cited as saying. “I don’t see those.”
Source: The Local, 20 February 2010 / Deutsche Welle, 21 February 2010 / Bloomberg, 23 February 2010

EDF-AREVA quarrel over reprocessing resolved?

As mentioned in the January 29 issue of the Nuclear Monitor there is a lot of rivalry between the French nuclear giants AREVA and EDF. In the beginning of January AREVA stopped removing spent fuel from reactors for reprocessing at the facility at La Hague. At the end of 2008, the companies agreed on a framework for contracts for the 2008-2040 period. But since mid-2009 they have not been able to settle disagreements over prices and volumes. On January 20, the two companies were given a two-week deadline by the French government to resolve their differences on this matter. On February 5, the two companies said in a statement, they would sign a contract covering “transportation, treatment and recycling” of used nuclear fuel before the end of March. The agreement reached by the two groups lays out conditions for applying the framework agreement of Dec. 19 2008, which set out a partnership covering treatment-recycling of used fuel, and reprocessed fuel fabrication, the firms said.

Source: Reuters, 5 February 2010

European Union heading for clash on funding ITER.

European governments want to slow down construction of the International Thermonuclear Experimental Reactor (ITER) because they are paying for the bulk of the construction costs and are concerned that the budget is spiraling out of control. The EU is covering 45% of the costs of building and running ITER, which is to be built in Cadarache, France. The other six partners (the US, China, Russia, India, Japan and South Korea) are each paying 9%.  Concerned about the mounting costs, the EU rejected a construction timetable proposed by ITER's administration at a meeting of participating countries on 18-19 November. The administration had proposed that ITER, which was launched in November 2006, should conduct its first experiments in 2018. But the EU's member states agreed in a position paper in November that a 2018 deadline was “not feasible”. (see Nuclear Monitor 698, 27 November 2009: “Fusion Illusions”) They reaffirmed this at a working group of the Council of Ministers on February 1. A 2018 deadline, however, is strongly backed by all non-EU countries involved in ITER, with the exception of the US, which has shown signs of flexibility. Officials said that the EU would prefer to make construction costs less painful by spreading them over a longer period of time. Concerns about the ballooning budget led the Commission last year to set up an expert group tasked with reviewing the construction costs. The group's report, released to member states in January, said that the construction costs alone could rise as high as 1.5bn Euro (compared to a 2001 estimate of 598 million Euro).Total EU-contribution of ITER-project costs could rise to 3,5 billion Euro (US$ ) instead of the 1.5 billion estimated in 2001.The countries participating in the ITER project will hold a special high-level meeting in Paris on 23-24 February to try to resolve the dispute.

Source: European Voice, 4 February 2010

Replies safety AP1000 & EPR of 'poor quality'.

UK nuclear regulators have criticised the "long delays" and "poor quality" of replies they have received from Westinghouse and Areva following safety reviews of their reactor designs, AP1000 and the European Pressurised Reactor (EPR). The Nuclear Installations Inspectorate has raised a number of serious issues on the design of the new reactors but in its latest report says the response from the two companies is less than expected.

The inspectors have already issued a formal 'Regulatory Issue' (RI) regarding the safety and control systems of the EPR and are now considering a RI on the shield building for the AP1000. Westinghouse is planning to use a new construction method for the reactor's shield building, using a sandwich of steel plates filled with concrete, rather than the conventional reinforced concrete. Regulators say they will have to be convinced the new techniques will be sufficient to withstand an accident, including a crash of a large aircraft. Westinghouse said it changed its construction methods in response to US regulations after 9/11 requiring it to withstand an aircraft impact.

Source: N-Base Briefing 642, 10 February & 643, 17 February 2010

Kakadu mine: Uranium contamination 5400 times background.

Australia: environmental regulators for the office of the Supervising Scientist admitted to a Senate Estimates committee on February 9, that water with uranium concentrations 5400 times background and a cocktail of other radionuclides are seeping from beneath the tailings dam at the Ranger Uranium Mine in Kakadu National Park. The Office of the Supervising Scientist acknowledged to Australian Greens Senator Scott Ludlam that the contamination was occurring, and said that the estimated amount of 100,000 liters per day was based on modeling and not measurement. "The biggest surprise is that despite knowing about this leakage for years, the regulators don't know how much is seeping, where it is going, or how highly contaminated it is. The regulator suggested that directly sampling this contaminated water would be 'impractical.' I suggest that it is now essential", Senator Ludlam said. "The mining company ERA booked a 2009 profit in excess of A$270 million dollars (US$240m or 177m Euro) and yet the regulator won't compel them to undertake any water quality sampling under the tailings dam. That has to change." Uranium is only one of a number of radioactive elements present in the tailings dam – others include Thorium, Polonium, Radon, Radium, Bismuth, etc.

Source: Media release Australian Greens Party, 9 February 2010