Belgium and the END of nuclear power

Nuclear Monitor Issue: 
#800
4453
19/03/2015
Jim Green − Nuclear Monitor editor
Article

Belgium is a microcosm of the ageing nuclear power industry. The International Energy Agency predicts a "wave of retirements"1 − almost 200 reactor shut downs by 2040 − and Oilprice.com argues that it is unclear whether new build will offset the "tidal wave" of reactor shut downs over the next 20 years.2 Belgium is at the sharp edge of this new nuclear era: the Era of Nuclear Decommissioning, the END.

Belgium's seven reactors − all pressurized water reactors − are all operated by Electrabel, a GDF Suez subsidiary. Electrabel owns 100% of two reactors, 89.8% of four reactors and 50% of one reactor. EDF and SPE are the other companies with ownership stakes.3

When all seven reactors were operating, they supplied about half of Belgium's electricity. All are due to be shut down by the end of 2025. Belgium's nuclear phase-out law mandates the shut down of six reactors when they have operated for 40 years − with the exception of Tihange 1, which is due to be shut down in 2025 when it has operated for 50 years.

All seven reactors have been in the news over the past year:

  • Doel 1: Shut down when its 40-year licence expired in February 2015.
  • Doel 2: Now operating but due to be shut down in December 2015. GDF Suez / Electrabel is negotiating a possible licence extension for Doel 1 and 2 to operate for another 10 years, and seeking regulatory approval.
  • Doel 3 and Tihange 2: Offline since March 2014 due to concerns about the integrity of reactor pressure vessels; future uncertain.
  • Doel 4: Offline for more than four months in 2014 due to suspected sabotage of the high-pressure turbine. Now operating.
  • Tihange 1: Now in its fortieth year of operation but licensed to operate for another 10 years. Greenpeace has initiated a legal challenge against the licence extension, because of the failure to carry out an Environmental Impact Assessment and cross-boundary consultation in line with Belgium's obligations under the Espoo Convention (the Convention on Environmental Impact Assessment in a Transboundary Context). Court hearings are scheduled for March 24 and the judge is expected to present his verdict soon after.
  • Tihange 3: Briefly shut down following a fire in December 2014. Now operating.

Policies and politics

Nuclear power policies and laws have been in flux over the past two decades:3

  • In 1999, the government announced that reactor lifetimes would be limited to 40 years, and banned further reprocessing.
  • In 2003, the Belgian Parliament passed legislation banning the building of new power reactors and limited the operating lives of existing reactors to 40 years.
  • In 2009, the government decided to postpone the phase-out by 10 years, so that it would not begin before 2025. This would allow the licensing of reactor life extensions. Reactor operators agreed to pay a special tax of €215−245 million (US$227−259m) per year from 2010−14, and more thereafter. GDF Suez also agreed to subsidise renewables and demand-side management by paying at least €500 million (US$528m) for both, and it maintaining 13,000 jobs in energy efficiency and recycling.

However, an election in April 2010 occurred before the agreed proposals were passed by parliament and thus the nuclear phase-out law remains in place. In July 2012 Belgium's Council of Ministers announced that Doel 1 and 2 were to close in 2015 after 40 years of operation, but Tihange 1 would be permitted to operate to 2025. This was written into law in December 2013. The government said that it had rewritten the 2003 law so that its current stance could not be changed by decree, and therefore the timing of the phase-out "is now final."3,4

In December 2014 the Council of Ministers from the new ruling coalition government agreed that Doel 1 and 2 could continue operating for a further 10 years, to 2025. Energy minister Marie-Christine Marghem said that it was an "unconditional prerequisite" that the Belgian nuclear regulator − the Federal Agency for Nuclear Control (FANC) − approve licence extensions for the two reactors. She noted that Belgium's planned nuclear phase-out by the end of 2025 remains in place.4

The government decision to allow Doel 1 and 2 to continue to operate for a further 10 years was partly a result of problems with other reactors − in particular the outages of Tihange 2 and Doel 3 and uncertainty about their future. GDF Suez / Electrabel is in negotiation with the Belgian government over the Doel 1 and 2 licence extensions but an agreement has not yet been reached − hence the shut down of Doel 1 in February in accordance with the nuclear phase-out law. Further, the regulator FANC has not yet approved licence extensions for Doel 1 and 2.4

GDF Suez / Electrabel is unwilling to invest up to €600−700 million (US$634−740m) in necessary upgrades to Doel 1 and 2 unless the government provides a "clear legal and economic framework" to justify the investment. Negotiations include removal of the nuclear generation tax introduced by a previous government − according to the World Nuclear Association, that tax cost the company €397 million (US$419m) in 2014.5

As Rianne Teule, campaign director for Greenpeace Belgium, put it: "In order to agree to such a large investment, Electrabel demands 'a clear legal and economic framework'. Read: 'a good deal to reduce the investment risks'. It's the Belgian people who will pay the price, one way or another. If not through increased taxes, when Electrabel's payments to the state decrease, then through increased electricity prices when Electrabel passes on their investments to their clients."6

In 2012 the government passed laws increasing the tax on nuclear operators. The government set a total contribution from nuclear operators for 2012 of €550 million (US$581m), of which Electrabel had to pay €479 million (US$506m). In June 2013 Electrabel filed an appeal to Belgium's Constitutional Court, claiming the tax violated a protocol signed by the company and the federal government in 2009, which included a lower tax, and took no account of declining revenue from nuclear power generation. In April 2014 the Court of First Instance in Brussels rejected Electrabel's claim. The company appealed, but the appeal was rejected in July 2014. Electrabel said it would continue "to examine all potential legal means in order to defend its interests" and "examine all options concerning the future of its nuclear activities in Belgium."3,7

According to Greenpeace, nuclear power is part of the energy security problem, not part of the solution: "The reason for the potential electricity supply problem is Belgium's excessive dependency (55%) on unreliable nuclear power. A political decision to extend the lifetime of two old reactors will not mitigate this acute supply problem. It will take at least a year to implement the necessary safety upgrades, and to order and fabricate new fuel for them. Extending the legally fixed phase-out calendar will undermine investment in real climate solutions such as energy efficiency and renewables."8

Tihange 2 and Doel 3 − compromised reactor pressure vessels

Doel 3 and Tihange 2 were taken offline in 2012 when ultrasound testing suggested the presence of cracks in their reactor vessels. Further investigations indicated that the defects are so-called hydrogen 'flakes'. FANC allowed Electrabel to restart the reactors in May 2013. However the reactors were again taken offline in March 2014 after Electrabel reported that tests to investigate the mechanical strength of irradiated specimens of similar material "did not deliver results in line with experts' expectations".9 FANC said that "a fracture toughness test revealed unexpected results, which suggested that the mechanical properties of the material were more strongly influenced by radiation than experts had expected."10

In January 2015, FANC said the process to restart the reactors had been extended from April to July so that Electrabel could answer further questions. In February, FANC announced that additional inspections revealed more extensive flaking within the pressure vessels of the two reactors than previously identified. FANC said 13,047 flaw indications have now been found in the vessel of Doel 3 and 3,149 in that of Tihange 2. Further test results are expected by April.1,9

FANC Director General Jans Bens said: "This may be a global problem for the entire nuclear industry. The solution is to implement worldwide, accurate inspections of all 430 nuclear power plants."11

Shortly after approving the restart of Doel 3 and Tihange 2 in May 2013 − a decision that was contested at the time and seems unwise in hindsight − Bens was seriously downplaying nuclear risks: "The harbour of Antwerp is being filled with windmills, and the chemical industry is next to it. If there is an accident like a break in one of the wings, that is a guillotine. If that goes through a chloride pipe somewhere, it will be a problem of a bigger magnitude than what can happen at Doel. Windmills are more dangerous than nuclear power plants."12

Two materials scientists have said the unexpected flaws in Doel 3 and Tihange 2 could be related to corrosion from normal operation, with potential implications for reactors worldwide. Prof. Digby MacDonald said: "The consequences could be very severe ... like fracturing the pressure vessel. Loss of coolant accident. This would be a leak before break scenario. ... My advice is that all reactor operators, under the guidance of the regulatory commissions should be required to do an ultrasonic survey of the pressure vessels. All of them." Prof. Walter Bogaerts said: "If I had to estimate, I would really be surprised if it ... had occurred nowhere else.13,14

Electrabel reacted to the latest news by saying that it may be willing to "sacrifice" one of the two reactors to allow destructive testing to learn more about the problem.15

Doel 3 and 4: Fire and sabotage

On 1 December 2014 at 10:30am, a fire began in the electrical substation transformer building at Doel and led to an emergency shutdown of reactor #3. The fire was put out by the local fire service and the reactor was restarted at 5am the following day.16 Fires at nuclear power plants pose significant risks to reactor safety due to the potential disruption of the electrical supply to vital reactor safety functions. The risks in Belgium are all the greater because of the high population density and the concentration of seven reactors at just two sites.17

Sabotage at Doel 4

The Belgium nuclear industry was shaken on 5 August 2014 when it was revealed that sabotage had caused, in Electrabel's words, "significant damage" at Doel 4. Lubricant had been discharged from the high-pressure turbine through a valve which had probably been opened deliberately by a worker. Some 6,000 professionals from 15 companies participated in the repair of the turbine. The repair involved the manufacture of 2500 blades at four plants in China, Croatia, Italy and Switzerland.18 The reactor was restarted on December 19.19

The END of nuclear power

When the last reactor is shut down in 2025, that won't be the end of Belgium's nuclear program but the beginning of the END − the Era of Nuclear Decommissioning.

In addition to the decommissioning of seven reactors, Belgians will somehow have to manage: high-level nuclear waste currently stored at Dessel and at reactor plants; larger volumes of low- and intermediate-level waste; and other nuclear facilities now in various stages of decommissioning including a MOX fuel fabrication plant and the Eurochemic reprocessing plant at Dessel.

References:

1. International Energy Agency, 2014, 'World Economic Outlook 2014', www.worldenergyoutlook.org
2. Nick Cunningham, 19 Feb 2015, 'Is There Any Hope Left For Nuclear Energy?', http://oilprice.com/Alternative-Energy/Nuclear-Power/Is-There-Any-Hope-L...
3. World Nuclear Association, 17 Feb 2015, 'Nuclear Power in Belgium', www.world-nuclear.org/info/Country-Profiles/Countries-A-F/Belgium/
4. WNN, 12 Feb 2015, 'Belgian reactor shutdown imminent', www.world-nuclear-news.org/C-Belgian-reactor-shutdown-imminent-1202156.html
5. WNA Weekly Digest, 27 Feb 2015, http://us1.campaign-archive2.com/?u=140c559a3b34d23ff7c6b48b9&id=b933e03098
6. Rianne Teule, 22 Dec 2014, 'Belgium's government is Electrabel's slave', www.greenpeace.org/international/en/news/Blogs/nuclear-reaction/belgiums...
7. World Nuclear News, 18 July 2014, 'Belgian court rejects nuclear tax complaint', www.world-nuclear-news.org/C-Belgian-court-rejects-nuclear-tax-complaint...
8. Eloi Glorieux, 13 Sept 2014, 'Belgium's nuclear reactors are phasing themselves out', www.greenpeace.org/international/en/high/news/Blogs/nuclear-reaction/bel...
9. WNN, 17 Feb 2015, 'Further flaws found in Belgian reactor vessels', www.world-nuclear-news.org/RS-Further-flaws-found-in-Belgian-reactor-ves...
10. FANC, 13 Feb 2015, 'Doel 3/Tihange 2: new update',
www.fanc.be/nl/news/doel-3/tihange-2-new-update/745.aspx
11. 13 Feb 2015, 'Veel meer scheuren in kerncentrales dan gedacht', http://deredactie.be/cm/vrtnieuws/binnenland/1.2238955
12. Justin McKeating, 23 May 2013, 'Fact not fiction: Renewable energy is safer than nuclear power', www.greenpeace.org/international/en/news/Blogs/nuclear-reaction/fact-not...
13. Greenpeace, 17 Feb 2015, 'Thousands more cracks found in Belgian nuclear reactors, Belgian regulatory head warns of global implications', www.greenpeace.org/international/en/press/releases/Thousands-more-cracks...
14. Greenpeace, 15 Feb 2015, 'Nuclear Reactor Pressure Vessel Crisis', www.beyondnuclear.org/storage/kk-links/Briefing_cracking_RPV_Greenpeace_...
15. Greenpeace, 17 Feb 2015, 'Thousands of cracks in Belgian reactors, potentially a global nuclear problem', www.greenpeace.org/international/en/news/Blogs/nuclear-reaction/cracks-i...
16. Greenpeace, 3 Dec 2014, www.greenpeace.org/international/en/high/news/Blogs/nuclear-reaction/bel...
17. Bart Martens, December 2014, 'De Economische Impact van een Kernramp In Doel', study commissioned by Greenpeace Belgium, www.greenpeace.org/belgium/Global/belgium/report/2014/RapportNL.pdf
18. WNN, 5 Dec 2014, 'Doel 4 restart approaches', www.world-nuclear-news.org/C-Doel-4-restart-approaches-0512145.html
19. 19 Dec 2014, 'Doel 4 reactor reopens', http://deredactie.be/cm/vrtnieuws.english/News/1.2186676

Belgium: three reactors offline

Nuclear Monitor Issue: 
#790
04/09/2014
Article

Reactor #4 at Belgium's Doel power station shut down automatically on August 5 after "significant damage" was inflicted on a high-pressure steam turbine. The reactor will remain out of operation until at least the end of this year, Electrabel said. The reactor shut down following the loss of oil in its steam turbine. Initial inspections found that the oil had been discharged through a valve which had probably been left open by a worker, according to Electrabel. Belgium's nuclear safety regulator, the Federal Agency for Nuclear Control (FANC), said the oil loss probably resulted from "voluntary manual intervention." A spokesperson for GDF Suez, Electrabel's parent company, said the oil loss resulted from "intentional manipulation". Electrabel, FANC and the Public Prosecutor of Dendermonde municipality are investigating.1

In addition to the Doel 4 incident, the Doel 3 and Tihange 2 reactors are offline because of cracks in steel reactor casings. FANC ordered the temporary shut down of the two reactors in 2012 for inspections when ultrasound testing suggested the possible presence of cracks in their reactor vessels. Further investigations indicated that the defects are so-called hydrogen 'flakes' and were introduced during the manufacturing process.2

In early 2013, FANC set out a list of 16 requirements, with 11 to be met before the reactors could restart. Electrabel submitted an action plan and the reactors restarted in May 2013. But they were closed again in March 2014 after additional tests on hydrogen flakes suggested they may affect the mechanical properties of their reactor vessels. The latest outages were expected to last about six weeks, but the reactors remain offline awaiting the results of further tests.

Belgian state media VRT reported that interim test results show the vessels are weakened by the cracks and may need to remain closed until some time next year or may even remain shut permanently. Electrabel responded: "The tests are making good progress and it is totally premature to draw conclusions from them. The first partial results do not in any case allow us to anticipate a definitive shut down. Once tests are completed, a report will be sent to the FANC, which will in turn decide on the restart of the power plants." The Atomic Power Review blog suggests that the outcome may be ongoing operation of the reactors, but with restrictive operating limits.

In addition to safety risks and sabotage allegations, another concern is that FANC chief Jan Bens appears to have a slender grasp on reality. He said in May 2013: "The harbour of Antwerp is being filled with windmills, and the chemical industry is next to it. If there is an accident like a break in one of the wings, that is a guillotine. If that goes through a chloride pipe somewhere, it will be a problem of a bigger magnitude than what can happen at Doel. Windmills are more dangerous than nuclear power plants."3

References:

1. www.energylivenews.com/2014/08/15/belgian-nuclear-power-plant-tampered-w...

www.world-nuclear-news.org/RS-Significant-damage-to-Doel-4-turbine-15081...

http://uk.reuters.com/article/2014/08/14/belgium-nuclear-doel-idUKL6N0QK...

http://atomicpowerreview.blogspot.com.au/2014/08/doel-3-and-tihange-2-un...

2. www.world-nuclear-news.org/C-Electrabel-reschedules-Tihange-1-outage-220...

http://atomicpowerreview.blogspot.com.au/2014/08/doel-3-and-tihange-2-un...

www.world-nuclear-news.org/RS-Regulator_OKs_Belgian_reactor_restart-1705...

www.enerwebwatch.eu/fissures-Doel-t17.html?langnav=en

3. www.greenpeace.org/international/en/news/Blogs/nuclear-reaction/fact-not...

About: 
Doel-4Doel-3Tihange-2

Pressure on UK government increases: companies want more subsidies

Nuclear Monitor Issue: 
#749
4231
11/05/2012
Pete Roche
Article

More and more companies are unsure about investing in new nuclear power plants in the UK. The latest companies that threaten to pull out and putting more pressure on the government to subsidize nuclear power through all kind of mechanisms, are GDF Suez and Centrica.

Centrica, the only British company in the running to build a new generation of nuclear power plants in the UK, has threatened to pull out. Executives at Centrica have warned the government that the plan hangs by a thread and could be scrapped if the company does not receive assurances about the future price of nuclear-generated electricity. Some of the government’s reforms, will be set out in the Queen’s Speech, which will set out the government's legislative plans for the next year. One element is long-term contracts that would guarantee a steady rate of return over the lifetime of a new plant – so-called “contracts for difference”. (The Queen's Speech is on May 9, unfortunately right after the deadline for this issue of the Nuclear Monitor.)

Contracts for Difference are effectively a long-term contract to buy nuclear power at a guaranteed price. If the market price is below the fixed price the Government would pay the reactor operator the difference. If the market price was above the contract price the operator would have to pay the  government.

The government has tried to help investors by proposing sweeping reforms of Britain’s electricity market, designed to attract investment in low-carbon electricity generation. As part of that, new nuclear plants will receive a guaranteed price for electricity. But the actual level of support has yet to be determined. A person close to Centrica said. “If we don’t get the right answers, we won’t proceed.” Centrica is planning to build a new nuclear power plant at Hinkley Point in a joint venture with EDF Energy. Late March two German firms, E.On and RWE, pulled out of the Horizon Nuclear Power joint venture, planning to develop up to 6.6 GW new nuclear capacity.

Only a few days earlier in April, another company, GDF Suez, is threatening to abandon the plan to build a new reactor at Sellafield. Gérard Mestrallet, chairman and chief executive of GDF, said what was on offer – a fixed carbon price and a "contract for difference"  - was "not enough and something is missing". He wanted talks with the government about the right fixed or minimum price for producing nuclear energy.

The Guardian newspaper wrote that a document (leaked to the paper) clearly lays out plans to use "contracts for difference" to allow nuclear operators to reap higher prices for their energy than fossil fuel plants. Fiona Hall, leader of the Liberal Democrats group in the European parliament said she now had no doubt that the contract for difference was a subsidy. "Industry on all sides believe this is a subsidy." She wants the UK court of auditors as well as the European commission to give a legal ruling on the issue and believes any subsidy runs against the coalition agreement.

The plans will further inflame rows over energy policy for the Liberal Democrats –who form the government with the Conservatives, and fought the general election firmly opposing an expansion of nuclear power.

A report from the Times newspaper on May 7, said French nuclear company EDF had raised the cost of building a nuclear power plant to 7 billion pounds (US$11.3bn, 8.7bn euro) from 4.5 billion pounds last year. "If the latest cost figures are true, new nuclear power plants in the UK are not commercially viable," Citi analyst Peter Atherton told Reuters. Based on the new figures, nuclear would be the most expensive form of electricity generation, exceeding even offshore wind, he said.

Sources: Guardian, 16 & 20 April 2012 / Financial Times, 20 April 2012 / Reuters, 8 May 2012
Contact: Pete Roche
Email: rochepete8[at]aol.com
Web: www.no2nuclearpower.org.uk/

About: 
WISE

In brief

Nuclear Monitor Issue: 
#684
25/02/2009
Shorts

U.K.: What's in our dump?

The operators of the Drigg national low-level waste facility have asked former workers to tell them what is buried there. In an advert in local papers LLW Repository Limited asked workers who tipped nuclear waste into the site's open trenches over a 25-year period from 1960 to try and remember what it was they dumped. The company said it did have records of what was dumped but they wanted "a clearer picture".

Cumberland News 14 February 2009


Greenpeace: illegal state aid Romania and Bulgaria.

On February 25, Greenpeace has filed complaints to the European Commission over alleged illegal state aid for the construction of two nuclear reactors in Romania and two in Bulgaria. The environmental organization argues that both countries violate EU competition rules. Jan Haverkamp, EU energy campaigner for Greenpeace, said: "We have been investigating for many months the unfair competition conditions that have been granted to the nuclear sector in Romania and Bulgaria. We have now submitted the evidence we have collected to the European Commission, and are calling for urgent action to correct these flagrant market distortions."

The Romanian government earmarked 220 million Euro for the Cernavoda 3 and 4 nuclear power plant. On top of this, the state spent EUR350 million in taxpayers´ money for the purchase of heavy water for the new power station, as well as EUR800 million to increase the capital of state utility S.N. Nuclearelectrica - S.A., with the purpose of supporting its financial contributions to the project.

The Bulgarian government has invested 300 million Bulgarian Leva (154 million Euro) in state utility NEK for the construction of the Belene nuclear power station, as well as another 400 million Leva (205 million Euro) in NEK's parent holding BEH, partly also meant for Belene. According to Greenpeace, all of these investments are in violation of EU competition law.

Press release, Greenpeace EU Unit, 25 February 2009


EDF debt increased to nearly 25 billion Euro.

French energy group and the world’s biggest operator of nuclear power stations, EDF could be forced to sell some of its power stations in France to help to fund its £12.2 billion acquisition of Britain’s nuclear industry. EDF shocked investors by unveiling a fall of nearly 40 per cent in annual profits (slipped to 3.54 billion euro in 2008, compared with 5.6 billion Euro in 2007) and warning that its debt pile had increased to nearly €25 billion (US$ 32 billion) after a string of acquisitions, including those of British Energy and America’s Constellation Energy.

EDF, which is 85 % owned by the French State, is aiming to cut its debt by at least 5 billion Euro by the end of 2010 and much of this would be achieved through asset sales. A number of foreign energy companies, including Enel, of Italy, have previously expressed an interest in entering the French power market.

The Times (U.K.), 13 february 2009


GDF Suez pulls out of Belene!

An important victory and another sign that the Belene project is too risky! French utility GDF Suez has decided to pull out of Bulgaria's planned nuclear plant of Belene. GDF Suez's Belgian subsidiary Electrabel had been in talks to take part in German utility RWE's 49-percent stake in Bulgaria's 4 billion Euro plant. RWE confirmed it had not reached an agreement with GDF Suez but said it would continue to develop the project as planned. "Financial, technical, economic and organization questions are in focus and safety of course comes first in all our considerations," a RWE spokesman told Reuters. Sources familiar with the Bulgarian nuclear project have said the global financial crisis and tighter liquidity have made raising funding extremely difficult and that it was likely the plant's starting date would go beyond the planned 2013-2014.

GDF Suez is focusing on its other nuclear projects, a company spokesman said. The company is trying to grab a share of the nuclear revival with plans to take part in the second and possibly the third new-generation French nuclear reactors as well as in nuclear power projects in Britain, Romania and in Abu Dhabi.

Reuters, 28 February 2009


More delays for Rokkasho.

The commercial start-up of Japan’s Rokkasho reprocessing plant has suffered a further delay. On January 30, its owner, Japan Nuclear Fuel Ltd (JNFL), filed an application with the Ministry of Economy, Trade and Industry (METI) to change its construction plan, pushing the scheduled completion date of the plant back to August 2009. A few years ago JNFL had planned to commence full operation of the plant in November 2007.

Groups and individuals have been campaigning against this plant ever since 1985, when Aomori Prefecture agreed to allow it to be constructed. If the Rokkasho reprocessing ever operates at full capacity, it will reprocess 800 tons of spent fuel and extract about 8 tons of plutonium per year. In the course of regular operations, when spent fuel assemblies are cut up (shearing), radioactive gases are released from the chimney stack. These include radioactive isotopes of krypton, xenon, iodine, cesium, etc.. Later in the process, other radioactive materials are released into the sea as liquid waste. These include tritium, carbon-14, iodine-129, plutonium, etc.. It is said that a reprocessing plant releases as much radioactivity in one day as a nuclear reactor releases in one year.

In addition, there are international concerns that the operation of the Rokkasho reprocessing plant will accelerate trends towards nuclear proliferation. The process used at Rokkasho will produce a 1:1 mixed oxide of plutonium and uranium. The Japanese government says that it is difficult to produce nuclear weapons from this. However, this is not true. Scientists in the US, and also the International Atomic Energy Agency, recognize that this material can readily be transformed into nuclear weapons.

Nuclear Engineering International, 18 February 2009 / Nuke Info Tokyo (CNIC)


U.K.: Leaked for 14 years.

Radioactive waste leaked from a decontamination unit at the Bradwell nuclear power station for 14 years, Chelmsford Crown Court was told late January. The operators, Magnox Electric, were found guilty of allowing unauthorized disposal of radioactive waste from 1990 to 2004 when the problem was discovered. The court was told the leak was caused by poor design and no routine inspection or maintenance. Chief inspector for the Nuclear Installations Inspectorate, Mike Weightman, said it was not possible to "inspect or check every feature of a complex plant" but once the leak was discovered regulators took quick action.

N-base 601, 11 February 2009


Iraq takes first step to nuclear power, again….

On February 22, Iraqi Electricity Minister Karim Wahid says Baghdad is taking initial steps to construct the country's first nuclear power plant in cooperation with France. "I am willing to enter into contacts with the French nuclear agency and to start to build a nuclear power plant, because the future is nuclear," said Wahid. Iraq had sealed a contract with France to construct a nuclear reactor during Saddam Hussein's regime in 1976. The construction of the Osirak reactor however remained unfinished after Israeli warplanes bombed the facility in 1981. Tel Aviv accused the regime of building nuclear weapons. In the 1990 Iraq was accused of having a secret nuclear weapons program. Already in 1991 in the first few days of Gulf War I Iraqi nuclear energy capability (research reactor, hot-cells, etc.) was said to be destroyed by the US-led international coalition. However, in the decade that followed Iraq was still accused of having a covert nuclear program, but in search of such a program, after the Gulf War-II in 2003 nothing was found.

Press TV (Iraq), 22 February 2009 / Laka Foundation, sources 1992 & 2003


France: TV show reveals radioactive risk.

Fears that radioactive material taken from France’s old uranium mines has been used in construction have been raised by a TV documentary. According to investigators for the program Pièces à Conviction (Incriminating evidence), there are many sites where radioactive material is a potential health risk including schools, playgrounds, buildings and car parks. Very little uranium is now mined in Europe, but France carried out mining from 1945 – 2001 at 210 sites which have now been revealed by IRSN, the Institute of Radioprotection and Nuclear Safety on its website. Problems stem from millions of tons of reject rock which contained small amount of uranium which are still stocked at some of the sites along with 50 million tons of waste from extraction factories.
The documentary on France 3 also revealed that some reject rock has also been used as construction rubble in areas used by the public, that there have been some radioactive leaks into the environment from waste and that some “rehabilitated” areas where building has been taken place had been contaminated with radon. Before the program went out Areva had lodged a complaint about it with the Conseil Supérieur de l’Audiovisuel concerned that its intention was to make accusations against the firm. The program makers said they had “opened a national debate on uranium waste in France”.

The Connection (Fr.), 13 February 2009


Largest Pu transport ever from Europe to Japan.

Secret preparations are underway in Britain and France for shipping 1.8 tons of plutonium, the largest quantity of plutonium ever shipped by sea. The plutonium is contained in 65 assemblies of MOX (mixed plutonium and uranium oxide) fuel and is being shipped to Japan for use in the nuclear power plants of three Japanese electric utilities. No details have been revealed, but it is reported that the fuel will be transported by two British-flagged vessels, escorting each other.

The vessels are to depart Europe anytime on or after March 1st. Neither the hour of departure nor the maritime route to be used will be revealed before the ships depart. The United States must approve the transport plan before the shipment can proceed. The MOX fuel to be transported has been fabricated in France by Areva NC. The three possible routes for the shipment are around the Cape of Good Hope and through the South Pacific, around South America, or, through the Panama Canal.

Japanese electric utilities hope the fuel to be shipped will start its troubled MOX fuel utilization program which was to begin a decade ago in 1999. Many more shipments are scheduled to follow and could take different routes.

Green Action (Japan) Press Release 24th Feb 2009


IAEA: Syrian uranium-traces manmade.

The International Atomic Energy Agency (IAEA) has said traces of uranium taken from the site of an alleged nuclear reactor in Syria were manmade. The report by the IAEA on the Dair Alzour site puts strong pressure on Damascus as it rejects the Syrian explanation for the presence of uranium.

The IAEA-report says that after an initial visit in June 2008, which revealed the presence of processed uranium, inspectors had not been allowed back to Dair Alzour and other sites where debris might have been stored, on the grounds they were "military installations".

IAEA denounces the Syrian government for its lack of cooperation with the agency's inquiry. "Syria has stated that the origin of the uranium particles was the missiles used to destroy the building," the IAEA report says. "The agency's current assessment is that there is a low probability that the uranium was introduced by the use of missiles as the isotopic and chemical composition and the morphology of the particles are all inconsistent with what would be expected from the use of uranium-based munitions."

The IAEA says Israel also failed to cooperate, but its findings give weight to the Israeli and US allegation that Dair Alzour was a secret reactor intended for eventual production of weapons. The report explicitly questions Syria's denials.

Circulation of the IAEA-report is restricted; it cannot be released to the public unless the IAEA Board decides otherwise. However, it can be found at: http://isis-online.org/publications/syria/IAEA_Report_Syria_Feb_2009.pdf

Guardian, 19 February 2009