You are here

plutonium

Japan's troubled plutonium program

Nuclear Monitor Issue: 
#698
5996
27/11/2009
Green Action Japan
Article

Japan's beleaguered 'pluthernal' program, MOX (mixed plutonium-uranium oxide) fuel use in commercial power plants, got off to a troubled start at Kyushu Electric's Genkai Unit 3 Nuclear Power Plant Unit 3 in Saga Prefecture on November 5, with the use of 16 MOX fuel assemblies. Full-time operation of the reactor is scheduled to begin December 2.

A round-the-clock sit-in began on the same day in front of Kyushu Electric headquarters in Fukuoka City and messages of support are pouring in from around the country. In less than two days 673 NGO groups signed on to protest and petition METI, Kyushu Electric, and Saga Prefecture demanding that use of MOX fuel at Genkai not go forward. The number of sign-on groups continue to grow.

Over 460,000 citizens are demanding that use of MOX fuel at Genkai be suspended. This and Kyu-shu Electricâ's rush to start use of MOX fuel caused an unprecedented move by the Saga prefectural legislature last month to demand that the utility rescind its original 2 October start-up date, which it did.

On 28 October Japan's nuclear regulator NISA (Nuclear Industrial Safety Agency) admitted that there are no legal grounds for the government's criteria for imported fuel assembly inspection of MOX fuel. This admission was made to an Upper House Diet office. Citizens, and national and Saga prefectural legislators demanded that NISA come to Saga to explain. NISA is yet to do so.

The 'pluthermal' program is one part of Japan's troubled plutonium program. The other two parts which are in deep trouble are the fast breeder program and reprocessing of spent nuclear fuel. Commercialization of the fast breeder reactor program has been delayed 8 times and is nearly 80 years behind original schedule (set for early 1970s, now set for 'by 2050'.) Commercial operation of the Rokkasho reprocessing plant has been delayed 17 times. Completion of active tests is now set for October 2010. However, with a dysfunctional high-level waste vitrification facility, the future of Rokkasho is murky.

On 7 October, NISA stated that it couldn't deny the possibility that the same quality fuel Kansai Electric rejected in August is in Genkai's MOX fuel. (Kansai Electric rejected one-quarter of the fuel that had been manufactured for use in its Takahama Unit 3 and 4 reactors.) Both utilities -- MOX fuel was fabricated at Areva -- MELOX plant in Marcoule, France.

Subsequently, Kyushu Electric refused to disclose pertinent information concerning its self-inspection criteria, stating that Mitsubishi Heavy Industries, their principle contractor for MOX fuel fabrication would not allow the disclosure. (The same kind of information has been released by Kansai Electric and their principle contractor Nuclear Fuel Industries, Ltd.) Kyushu Electric stated that MELOX as-sured them that Kyushu's MOX fuel had no problems like the one found in Kansai Electric MOX fuel, but the utility admitted they were not shown data to confirm this was correct. The concentration of plutonium in Genkai's MOX fuel is unprecedented and exceeds even that used in France.

German nuclear authorities (BMU) initiated an investigatation after Kansai Electric's rejection of Areva MOX fuel. BMU is reported to take the issue seriously. The status of the investigation is unknown.

'The Japanese government spends 64% of its R&D for energy on nuclear. This program to utilize plutonium is the biggest stumbling block to development of renewable energy and energy efficiency in Japan. Prime Minister Hatoyama is woefully ignorant about this reality. The new government must become aware that this detrimental program is merely a lobbyist and bureaucratic haven. It should shut down the program immediately,' stated Aileen Mioko Smith, executive director of Green Action, a Japanese citizens organization campaigning to stop Japan's plutonium program.

The shipment of MOX fuel for use at Genkai and two other plants which took place this spring did not meet MLIT (Ministry of Land, Transport and Infrastructure) requirements. On 26 February, twenty Diet members signed on to an open letter addressing this concern. One of them includes the current MLIT minister Seiji Maehara, and, two other ministers in the Hatoyama government. Future shipments can-not meet this requirement (MOX fuel cask drop test) at this point.

In April a report commissioned by 70 nuclear free local authorities in the UK found that the British-flagged vessels which transport the MOX fuel from Europe to Japan have serious design flaws. Japan's program is dependent on these shipments since there is no commercial MOX fuel plant in Japan to supply electric utilities. Japanese nuclear transports are protested by dozens of en route countries.

Japan's pluthermal program start-up is a decade behind schedule due to a quality control data falsification scandal of Kansai Electric MOX fuel in 1999, citizen protest, nuclear inspection data falsification by Tokyo Electric in 2002, etc. In June electric utilities announced a multi-year delay in the deadline to use MOX fuel in 16-18 reactors, originally scheduled for 2010.

Source: Green Action (Kyoto, Japan) news release, 5 November 2009
Contact: Aileen Mioko Smith at Green Action, Suite 103, 22-75, Tanaka Sekiden-cho, Sakyo-ku Kyoto 606-8203 Japan. Tel: +81-90-3620-9251, E-mail: info@greenaction-japan.org, Web: www.greenaction-japan.org

France: nearly 5x as much plutonium in glove boxes as expected

Nuclear Monitor Issue: 
#696
5982
23/10/2009
WISE Amsterdam
Article

The Nuclear Safety Authority, (Autorité de Sûreté Nucléaire, ASN) France’s nuclear regulator, has suspended decommissioning of the ATPu facility at Cadarache and castigated French Atomic Energy Commission (operator CEA), after discovering that the plutonium inventory was much higher than thought.

The Nuclear Safety Authority said that the Atomic Energy Commission (Commissariat a l'Energie Atomique, CEA) had discovered that plutonium deposits inside glove boxes at the ATPu facility at Cadarache had been underestimated as early as June 2009 but had failed to notify it of the underestimation until early October.

The plant produced plutonium-containing mixed oxide (MOX) fuel pellets for 40 years, during which time it was estimated to contain a total of 8 kg of plutonium in deposits that gradually built up in inaccessible parts of some 450 glove boxes. However, around 22 kg of plutonium deposits have been recovered since decommissioning began in March 2009, and the CEA now estimates that the total could be in the region of 39 kg.

 Although the incident itself was without any safety consequences, the regulator noted that underestimation of the quantities of plutonium reduces safety margins calculated to prevent criticality accidents: "ASN considers the lack of detection of this underestimation during the operating period of the installation, as well as the late reporting of this event to the ASN, reveal a gap in safety culture."

Because the operators of Cadarache (which has 19 nuclear installations and the international ITER fusion demonstration project) have absolutely no idea how much plutonium they were supposed to be safeguarding, we cannot be sure how much of this plutonium may have been stolen to make nuclear weapons or is otherwise unaccounted for? We’ll never know – until it’s too late, obviously .

ASN was further incensed by what it considered the late reporting of the matter. A statement from the regulator said that it had only been informed of the underestimation on 6 October and that its inspection on 9 October confirmed that the CEA had known about the discrepancy since June. The ASN was highly critical of this delay, which caused it to raise the incident from Level 1 to Level 2 on the International Nuclear Event Scale (INES). However, CEA has since responded with an alternative timeline in which it verbally informed ASN of the discrepancy on 11 June. Furthermore, CEA said that the discrepancy had been recognized by the Euratom inspectors on 23 June as well as other officials from the Institute of Radiation Protection and Nuclear Safety (IRSN) on 1 and 2 July.

French energy and ecology minister Jean-Louis Borloo issued a statement calling for "complete transparency" on the situation: "This transparency and safety requirements are essential conditions for the supply of electricity from nuclear sources," he said. "They will be respected."

The ATPu started up in 1964 and was operated by French fuel cycle company Areva from 1991 until its closure in June 2008.

Sources: World Nuclear News, 16 October 2009 / ACDN Website, 15 October 2009 / Nuclear Reaction, 20 October 2009
Contact: Sortir du nucleaire, 9 rue Dumenge, 69317 LYON cedex 04, France
Tel: +33 4 78 28 29 22
Email: contact@sortirdunucleaire.fr
Web: www.sortirdunucleaire.fr

About: 
Sortir du Nucleaire

In brief

Nuclear Monitor Issue: 
#682
22/01/2009
Shorts

German Nuclear Waste Site in Danger of collapsing.
The Federal Office for Radiation Protection (BfS) had learned late last year that pieces of the ceiling of the 750-meter deep chamber were unstable and could collapse on top of the 6,000 radioactive waste drums below. The information about the Asse nuclear waste site  (an old salt mine) was posted discreetly on the radiation office's Web site late Wednesday, January 14. The BfS said it could not rule out damage to the waste containers should the Asse site ceiling collapse, but gave its reassurances that it would reinforce the seals of the chamber with concrete to stop any radioactive dust or air escaping. The office said the measures were only a precaution and that there was no immediate danger posed by the site. It said the waste inside the chamber contained only low-levels of radioactivity. The site has not been used for fresh radioactive storage since 1978, with environmental groups regularly calling for waste there to be removed and stored in a safer location.

Deutsche Welle, 16 January 2009


Brazil to start enriching uranium at Resende. Industriás Nucleares do Brasil (INB) has been issued a temporary licence by the Brazilian Nuclear Energy Commission (CNEN) to start enriching uranium on an industrial scale at its Resende plant.

INB has held an environmental licence to enrich uranium since November 2006, but the plant's operating permit, which is valid for one year, has been now been amended by the CNEN. Production of enriched uranium is expected to begin in February, with some 12 tons of enriched uranium expected to be produced by the end of 2009. The ultra-centrifugation enrichment technology used at the plant was developed by the Naval Technology Centre in Sao Paulo (CTMSP) and the Institute of Energy and Nuclear Research (IPEN). However, the technology is similar to Urenco's technology.

The Resende plant currently has two cascades of centrifuges. The first cascade commenced operation in 2006 and the second was expected to do so in 2008. Stage 1 - eventually to be four modules totalling 115,000 SWU per year and costing US$170 million - was officially opened in 2006. Each module consists of four or five cascades of 5000-6000 SWU per year. It is planned that a further eight cascades are installed by 2012, which will take the capacity to 200,000 SWU. By that time, INB is expected to be able to produce all the enriched uranium used in the Angra 1 reactor and 20% of that used in Angra 2. Those are the country's only operating power units at the moment, although plans to complete Angra 3 are advancing and many more reactors are expected in time.

Up until now, uranium used to fuel Brazil's nuclear power reactors has been sent as uranium concentrate to Cameco in Canada to be converted into uranium hexafluoride (UF6) gas, which has then been sent to Urenco's enrichment plants in Europe. After enrichment, the gas has been returned to Brazil for INB to reconvert the UF6 gas to powder, which is then used to produce nuclear fuel pellets.

World Nuclear News, 14 January 2009


Australia/UK: Plutonium secretly dumped at sea?
Declassified UK Government files show that 500g of plutonium and about 20 kg of radioactive wastes were secretly removed from the 1950s bomb test site at Maralinga in Australia. The UK Government removed the wastes in 1978 and although there is no official record of what happened to it the suggestion in the files is that it was secretly dumped at sea.

N-base Briefing 596, 7 January 2009


Sellafield privatisation: Rushed liabilities deal
Commercial insurance companies refused to consider any policy regarding liabilities for an accident at Sellafield which might be bought in courts outside the UK which were not party to existing liability conventions. Energy minister Mike O'Brien told the House of Commons the Nuclear Decommissioning Authority approached the nuclear insurance market in 2007 when it was preparing the contract for a private company to run Sellafield. The Government and NDA eventually indemnified the private companies chosen to run Sellafield and the Drigg waste facility against any costs arising from an accident - even if it was shown to be the fault of the commercial company.

Meanwhile, documents obtained under the Freedom of Information Act show the lengths ministers and civil servants took to prevent MPs from having the opportunity to discuss the decision to make the contract for running Sellafield more financially attractive to private companies. The Government agreed to take over responsibility for the costs of any accidents at Sellafield after the preferred bidders, Nuclear Management Partners, said it would not sign the contract unless it was indemnified against all costs. Ministers abandoned normal procedures to ensure that by the time MPs learned of the arrangements it would be too late to make any changes.

N-base Briefing 596 & 597, 7 & 14 January 2009


Turkey: AtomStroyExport revises bid.
A consortium led by Russia's AtomStroyExport submitted a revised bid for the tender to build Turkey's first nuclear power plant minutes after the contents of its initial bid were announced. At 21.16 cents per kWh, the initial bid submitted by the consortium is nearly triple the current Turkish average wholesale electricity price of 7.9 cents per kWh. Turkish energy minister Hilmi Guller told a press conference that AtomStroyExport had submitted a revised price "linked to world economic developments". Although it would be unorthodox for a bid to be revised once submitted in the tender process, AtomStroyExport's is the only bid on the table and Guller suggested that there would be room for bargaining. The revised bid would be opened and assessed by Turkish state electricity company TETAS who would assess it before passing it on to the country's cabinet for approval. No details of the revised bid have been released.

Turkish plans call for the country's first nuclear power plant to be operational by 2014, with proposals for 10-12 reactors by 2020 but would-be reactor builders appear to be treading carefully. Although six parties participated in the tendering process for the country's first nuclear reactor, AtomStroyExport's consortium was the only one actually to submit a bid.

World Nuclear news, 20 January 2009


Australia : no nukes to cut carbon emissions.
The Australian government  will not choose for nuclear power to help tackle climate change. The Australian Academy of Technological Sciences and Engineering - representing engineers and scientists – urged to do so in a report, calling the government to spend A$6 billion on researching ways to slash the carbon emissions from electricity generation. The academy's report says no single technology will solve climate change, and takes a look at everything from nuclear power to clean coal and renewable energy.
Federal Energy Minister Martin Ferguson responded by saying the government was committed to meeting its greenhouse gas reduction targets without turning to nuclear power. "It is the government's view that nuclear power is not needed as part of Australia's energy mix given our country's abundance and diversity of low-cost renewable energy sources," he said. "The government has a clear policy of prohibiting the development of an Australian nuclear power industry." The report's author Dr John Burgess said he was not disappointed by the minister's comments on nuclear power. "I guess what we're slightly concerned about is that without nuclear energy the other technologies have to work," Dr Burgess said.

The statement is important as the world is starting to prepare for the crucial Climate talks in Copenhagen, Denmark, December this year. If nuclear power will not get the support of major players (ie. financial state aid, subsidies via post-Kyoto flexible mechanisms as CDM and the Carbon Trade schemes) it will be considered and received as a major knock-out to the nuclear industry.

Business Spectator, 16 January 2009


Russian economic crisis decreases nuclear safety.
The nuclear industry in Russia is being negatively affected by the countries economic crisis; and the situation is expected to worsen in 2009. This is according to a recently released annual report by the states nuclear regulatory body. Ongoing job cuts at nuclear facilities include the personnel directly responsible for safety control. Activists call on the Russian government to quickly adopt a plan to insure public safety and nuclear security. The deteriorating social and economic situation in Russia is likely to result in significant drop of nuclear safety' level at many nuclear facilities. Some nuclear facilities have already seen jobs cut because of reduced national income due to declining oil prices and the global recession.  It is possible that further cut jobs in Russians and may bring back the nuclear proliferation problems related to illegal trade of radioactive materials. These radioactive materials can be used for building a "dirty bomb". According to governmental report, obtained by Ecodefense, staff cuts have been underway since 2007.

According to the recently released annual report written by the Russian nuclear regulator, Rostekhnadzor,  there have been "job cuts at facilities responsible for nuclear-fuel cycle of personnel responsible for safety control and maintenance". The report also criticises nuclear facilities management for "not paying enough attention to ensuring nuclear safety". In a disturbing criticism of iteself, Rostekhnadzor reports that it doesn't have enough safety inspectors to do it's own job properly.

Press release Ecodefense, 23 December 2008

Pages