Switzerland: closer to a nuclear phase-out or tactical pause?

Nuclear Monitor Issue: 
#726
6126
13/05/2011
Philippe de Rougemont, President, Sortir du nucléaire
Article

A referendum on the construction of three new 1600 MW nuclear power plants (NPP) was  to be held in 2013, for a planned grid connection in 2025. That was before the Fukushima catastrophe. Since then the federal department  in charge of energy decided to uphold the entire consultation process to "learn more" from the Japanese catastrophe.

When the nuclear catastrophe started to unfold at Fukushima-1 on march 11, the Minister for energy and infrastructures, Ms Doris Leuthard, a former nuclear lobby board member, decided to uphold the non-decisionary consultation process - mandatory under the new nuclear energy law - that was to lead to a decisionary referendum expected for 2013 (see Nuclear Monitor 676, 4 September 2008). The reason given for this decision was to analyse 3 new nuclear power plants projects using new knowledge gained at Fukushima. A country without sea coastline has no tsunami warning zone, but other residual risks exist, such as major breaches in large mountain dams that could drown nuclear installations, earthquakes or human errors.

The federal council ordered new studies, on the security of the 5 existing nuclear reactors and on future energy scenarios, including nuclear phase-out plans. At first the antinuclear campaign was relieved by this, until doubts started clouding the federal decision. Had Ms Leuthard been genuinely shocked by the new nuclear catastrophe, enough to halt a process that was supposed to lead to the building of at least one new nuclear power plant that she backed until then? Or was it a tactical decision, namely, a momentary suspension, not a grounding? Was she afraid Swiss citizens wouldn't vote according to plan this time, and simply decided to postpone the vote until momentary emotional considerations receded back to normal? Since 1984, three votes on nuclear phase out initiatives (formal proposals) have been put to vote. Each one failed to phase out nuclear power, apart from a 1990 vote, 4 years after Chernobyl, that imposed a 10 year moratorium on nuclear power plant constructions.

What are the current prospects for change on the energy issue outside of the federal council?

The Swiss Green party launched a new federal initiative, gaining political and NGO support. If voted into the constitution (in 3 to 5 years), it would bar construction of new nuclear power plants and limit life cycles of existing reactors to 40 years, with a last closure in 2024. The Socialist party, also in competition for new green votes, announced parliamentary initiatives to phase out nuclear power.

Major editorialists and conservative politicians have taken position against nuclear energy, before Fukushima this wouldn't have been expected. In June the Swiss parliament will hold sessions dedicated to future energy scenarios; will the anti-nuclear drive lose momentum or will this catastrophe act as a catalyst for change? Two weeks after Fukushima, a poll showed 87% of the population wanted a progressive nuclear phase out.

Source and contact: Philippe de Rougemont, President, Sortir du nucléaire, CP 1378  CH 1001 Lausanne
Email: pdr@sortirdunucleaire.ch
Web: www.non-au-nucleaire.ch/

In brief

Nuclear Monitor Issue: 
#715
03/09/2010
Shorts

No Nukes Asia Forum in Taiwan
Activist from Indonesia, Malaysia, Vietnam, Taiwan, Japan, Korea, the Philippines, Thailand and India wil hold their (almost) annual meeting in Taipei, from September 18- 22.

NNAF began in 1993 and unites Asian based antinuclear organizations. The forum always combines education and exchange with direct action and media outreach. This year the international delegation will travel to Taiwan’s nuclear power station no. 1 and 2 at the northeast coast and nuclear power plant no. 3 at the southeast coast. At the University of the capital Taipei a two-day program will discuss the danger of  nuclear power plants in earthquake prone areas, the debate on climate change and the role of nuclear power and the situation in the different countries.
Contact and more information: hsiujung.lee@gmail.com


Doctors against uranium.
The International Physicians for the Prevention of Nuclear War (IPPNW) on September 1 adopted a resolution at its International Council meeting in Basel, Switzerland, calling for a ban on uranium mining and the production of yellowcake (uranium oxide). The resolution described both processes as “irresponsible” and “a grave threat to health and to the environment”.
The resolution also describes uranium mining and yellowcake production as a “violation of human rights”. The right to life, liberty and security, to physical integrity, self-determination, the protection of human dignity, the right to clean water are just some of the rights that are afflicted by uranium mining and its processes, say the doctors. IPPNW calls for appropriate measures to ban uranium mining worldwide
Although many national branches of the IPPNW network have been campaigning against uranium mining and nuclear energy for many years already it is seen as a major breakthrough that now the international federation has taken a firm position and has committed itself to support campaigns against uranium mining.
Source and contact: IPPNW, Anne Tritschler, Tel.: +49 (0) 30-698074-14, tritschler@ippnw.de


Iran: Busher reactor finished after 36 years!
On August 21, Russia started loading fuel into the reactor at Iran's first nuclear power station Bushehr. The Bushehr plant is on the Gulf coast of southwest Iran. It is Iran's first nuclear power plant. Construction of two pressurized water nuclear reactors began in 1974 with the help of German contractor Siemens and French scientists. The Bushehr I reactor was 85 percent complete and the Bushehr II reactor was partially complete prior to the 1979 Iranian Revolution and the fall of the Shah. The project was halted and the site was then damaged during the 1980-88 Iran-Iraq war, and equipment was looted.

The project was later revived with Russian help but construction ran into repeated delays blamed by Russia on problems with receiving payment from Iran. Current plans are for one reactor to be launched. Bushehr will have an operating capacity of 1,000 MW.
Reuters, 21 August 2010


Sudan: 4 reactors in 2030.
Well, if you think you read it all…. Sudan plans to build a four-reactor nuclear power plant to "fill a gap in the energy needs" of Africa's largest country by 2030, Mohamed Ahmed Hassan el-Tayeb, head of Sudan's atomic energy agency, said on August 24. He also said that the International Atomic Energy Agency (IAEA) would help to build a research reactor and power plant for Sudan by providing expert training for staff, fellowships and feasibility studies.

He said Sudan was hoping for "a medium size four-unit power plant with each reactor producing between 300-600 MW per year". El-Tayeb said bidding for equipment and technology could begin in five years time and a further 10 years for construction of the plant, so it could be completed by 2030, costing between US$3-6 billion.

Currently 20% of the population has access to electricity.
Reuters, 24 August 2010


Nuclear power: Goal or means?
Vice President Boediono of Indonesia said on August 20, that a proposal to build a nuclear power plant in Indonesia was still on the table although he could not say when or where it may be built. “We will continue trying. Someday, somewhere we will build the nuclear power plant.”

More often than not it seems that nuclear power is rather a goal than a means to boil water (because that’s all there is to it, or not…?).
Jakarta Post, 20 August 2010


Radioactive boars on the rise in Germany.
Almost a quarter century after the 1986 Chernobyl nuclear meltdown in Ukraine, its fallout is still a hot topic in some German regions, where thousands of boars shot by hunters still turn up with excessive levels of radioactivity and considered potentially dangerous for consumption. In fact, the numbers are higher than ever before. The total compensation the German government paid last year for the discarded contaminated meat shot up to a record sum of  425,000 euro (US$558,000), from only about 25,000 euro ten years ago, according to the Federal Environment Ministry in Berlin. "The reason is that there are more and more boars in Germany, and more are being shot and hunted, that is why more contaminated meat turns up," spokesman Thomas Hagbeck told The Associated Press. Boars are among the species most susceptible to long-term consequences of the nuclear catastrophe 24 years ago. Unlike other wild game, boars often feed on mushrooms and truffles which tend to store radioactivity and they plow through the contaminated soil with their snouts, experts say.

However, boars are actually the beneficiaries of another ecological crisis — climate change. Central Europe is turning into a land of plenty for the animals, as warmer weather causes beech and oak trees to overproduce seeds and farmers to grow more crops the boars like to feast on such as corn or rape, said Torsten Reinwald of the German Hunting Federation.

"The impact of the Chernobyl fallout in Germany, in general, has decreased," said Florian Emrich, spokesman of the Federal Office for Radiation Protection. For example, radiation has ceased to be a problem on fields cultivated with commercial crops, he said. But forest soil in specific regions that were hit hardest after Chernobyl — parts of Bavaria and Baden-Wuerttemberg in southern Germany — still harbors high amounts of radioactive Cesium-137 which has a half life of roughly 30 years, Emrich said. In fact, the Cesium from the Chernobyl fallout is moving further into the ground and has now reached exactly the layer where the boars' favorite truffles grow. Therefore, the season for such truffles — a variety not eaten by humans — usually means a rising number of radioactive boars.
AP, 18 August 2010


Russian reactor too expensive for Belarus?
Alyaksandr Lukashenko said that Belarus might abandon plans to have its nuclear power plant project built by Russia and financed with a Russian loan, according to BelaPAN. The Belarusian leader said that the signing of an interstate agreement on the project had been postponed once again, and that the government did not reject the possibility of the plant being built by a contractor other than Russia s Atomstroiexport. Belarus chose Russia on the basis of "what they promised to us," Mr. Lukashenko noted. "They urgently demanded from us that they build this plant and then they started putting pressure on us for, I believe, purely subjective reasons. You know what the reasons are," he said.

Russia wanted Belarus to pay "in fact a double price," but Minsk refused, saying that there had been an agreement that the price would be "the same as in Russia," he said, adding that Belarus had agreed to pay the price at which the last nuclear power plant was built in Russia.
www.naviny.by, 16 August 2010

In brief

Nuclear Monitor Issue: 
#713
09/07/2010
Shorts

The IPPNW World Congress in Basel, Switzerland,  (August 25 – August 30, 2010) to also talk about nuclear power.
Nuclear weapons and disarmament are still hitting media headlines. The signing of the new START (Strategic Arms Reduction Treaty) was an important step towards the reduction of global nuclear arsenals. European governments are pushing for a withdrawal of US nuclear weapons from European NATO member countries. Leading politicians of several countries are calling for active and far-reaching reductions in the numbers of nuclear weapons in the interests of world security. It was hoped for that the Review Conference of the Non-Proliferation Treaty (NPT) in May in New York would bring further concrete measures. And although this did not happen the ‘Atomic Scientists’ decided to set back the Doomsday Clock one minute – from 5 minutes to 6 minutes to midnight.

On the other hand, some countries want to keep the prestige of being a nuclear power and some are becoming greatly interested in acquiring such power. Thousands of nuclear missiles still exist – decades after the end of the Cold War – on high alert, ready to be launched at a moment’s notice. Added to this, the interest of powerful companies in the military-industrial complex to continue building nuclear missiles is strongly influential. These companies put forward persuasive arguments for retaining the status quo through the use of intense political lobbying.

“Global Zero” is the desire of many millions of people and is also the vision of  the International Physicians for the Prevention of Nuclear War (IPPNW). Join them in sharing this vision in August at the 19th IPPNW World Congress in Basel, Switzerland. Traditionally the IPPNW only talks about nuclear weapons. This time their pre-conference programme also touches upon the issue of nuclear energy. Take this opportunity to discuss with them the important role ”civil” nuclear energy plays in increasing proliferation risks.
Check the programme at http://www.ippnw2010.org/


Italy: Regions have no say in siting nuclear reactors.
On June 30, Italy's highest court rejected an appeal by 10 Italian regions to have a say on the location of any nuclear power plants built.

Last July, the right wing majority in the Parliament adopted a law that gives extra power to the government in order to choose sites for new nuclear plants and provides the use of military forces to make its realization possible. On September 30, with the support of environmental organizations, 10 of 20 regions contested that law asking the intervention of the Constitutional Court. According to the regions the law violates the Italian Constitution by giving the government the power to decide without the consensus of local institutions. The June 30 ruling by the Constitutional Court effectively means the central government will have the final say on the site of the plants.

Nuclear power was abandoned in Italy nearly 25 years ago after a referendum in 1987. Enel and France's EDF would like to start building four nuclear power stations in Italy in 2013. Public opinion in Italy has been generally hostile to nuclear energy and local authorities had demanded a say in their approval.
Reuters, 23 June 2010 / Nuclear Monitor 702


After N-Korean 'nuclear breakthrough': xenon levels, eight times higher. Abnormal radiation was detected near the inter-Korean border days after North Korea claimed to have achieved a nuclear technology breakthrough, South Korea's Science Ministry said June 21. It failed to find the cause of the radiation but ruled out a possible underground nuclear test by North Korea, because there is no evidence of a strong earthquake that must follow an atomic explosion.
 

On May 12, North Korea claimed its scientists succeeded in creating a nuclear fusion reaction - a technology also necessary to manufacture a hydrogen bomb. South Korean experts doubted the North actually made such a breakthrough. On May 15, however, the atmospheric concentration of xenon - an inert gas released after a nuclear explosion or radioactive leakage from a nuclear power plant - on the South Korean side of the inter-Korean border was found to be eight times higher than normal.

Nuclear fusion as cause for the Xenon-measurement is very unlikely (to say the least). To start with: the alledged fusion breakthrough supposedly took place in mid-April and the half-lives of its radioisotopes are counted in hours or days. So a measurement almost a month  later is very unlike. But most important: a fusion reaction doesn’t produce fission products. Radioactive Xe isotopes, besides from a weapons test, can also be produced from operating a fission reactor with cracked fuel rods or from fission occurring in cooling water from released fuel. So possibly the higher levels could have been from built up Xe within a reactor containment vessel from an accident. A Science Ministry official said the wind was blowing from north to south when the xenon was detected and said it could have come from Russia or China, not necessarily from North Korea.
The Associated Press, 21 June 2010 / Armscontrolwonk.com, 21 June 2010


Nuclear projects in Baltic Region.
On June 16, antinuclear activists with protest banners greeted IAEA head Y.Amano and  Lithuanian Prime Minister A. Kubilius during their participation in the Roundtable discussion on "Regional nuclear energy projects" in Vilnius, Lithuania. Activists called to cancel development of the three nuclear energy projects in the Baltic region and to switch investments and cooperation to renewables and energy efficiency. Ostrovec nuclear power plant (Belarus), Baltic npp (Russia, Kaliningrad region) and the Visaginas nuclear power plant (Lithuania) are  primary targets for the criticism of environmentalists from Lithuania, Belarus and Russia. All these planned nuclear power plants face similar problems: safety, environmental, radioactive waste management, fake plans for investment.Later activists took part in the roundtable discussion as observers. Main issue there was that each country was convincing others how important their nuclear project is for the country and how good for the region. Lithuania was raising doubts about various aspects of Belarussian and Kaliningrad nuclear projects, promoting its own as "more transparent and safer".
Email: Lina Vainius, 17 June 2010


New name for GNEP: INFEC.
The Global Nuclear Energy Partnership Steering Group met in Accra, Ghana on June 16-17, 2010 and approved unanimously several transformative changes. This to "reflect global developments that have occurred since the Partnership was established in 2007".  The transformation includes a new name - the International Framework for Nuclear Energy Cooperation (INFEC)-- and the establishment of a new Statement of Mission. One of the main points of the Global Nuclear Energy Partnership (GNEP), announced by the United States in 2004, was to limit spread of enrichment (as well as reprocessing) technology. At the core of the strategy was the idea that countries that don't have fuel cycle facilities would refrain from acquiring them and accept the status of "fuel customers". Fuel services would then be provided by "fuel suppliers", who already have the necessary technology. There were doubts about the viability of this strategy from the very beginning.

The IFNEC acronym brings back echoes of the International Nuclear Fuel Cycle Evaluation (INFCE) program under the IAEA in the late 1970s. It too was set up on the initiative of the USA and worked on the "urgent need to meet the world's energy requirements," to make nuclear energy more widely available and "to minimize the danger of nuclear weapons proliferation without jeopardizing energy supplies or the development of nuclear energy for peaceful purposes" all with special attention for the needs of developing countries. One interesting difference was the inclusion of Iran as co-chair of INFCE's group on uranium enrichment availability.

Last year in June, the US. Department of Energy (DoE) decided to cancel the GNEP programmatic environmental impact statement (PEIS) because it is no longer pursuing domestic commercial reprocessing, which was the primary focus of the prior administration's domestic GNEP program. That decision followed a change in government policy on commercial reprocessing since president Obama took over from Bush.

Jordan formally announced that it will host the next meeting of the International Framework's Executive Committee in the fall of 2010. Some 25 countries have joined the GNEP.
Press release US. Department of Energy, 18 June 2010 / World Nuclear News, 21 June 2010 / Nuclear Monitor 691, 16 July 2009


China bends international rules to sell reactors to Pakistan.
China has agreed to sell two nuclear reactors to Pakistan. Under the Nuclear Suppliers Group’s (NSG) guidelines, countries other than China, France, Russia, the United Kingdom, and the United States (the five recognized nuclear weapon states) are not eligible to receive nuclear exports from NSG members unless they agree to inspections known as full-scope safeguards. Pakistan currently does not open all of its nuclear facilities to international inspections.

The US government “has reiterated to the Chinese government that the United States expects Beijing to cooperate with Pakistan in ways consistent with Chinese nonproliferation obligations.” Given that the US has signed a major nuclear deal with India – like Pakistan, a non-signatory to the Non-Proliferation Treaty (NPT) – the move smacks of hypocrisy. The US pushed the IAEA into conceding to country-specific safeguards for India’s reactors, then lobbied for country-specific concessions for India from the NSG. As a result, lucrative nuclear contracts are being signed by India and countries like France, Russia and the UK. As such, when experts cite the violation of the NPT’s international guidelines by the Pakistan-China civilian nuclear deal, the IAEA and NSG concessions to India give this posturing little credibility.

(More on the deal and its consequences: Nuclear Monitor 709, 12 May 2010: "China: US-India deal justification for selling reactors to Pakistan")
The Sunflower (eNewsletter of the Nuclear Age Peace Foundation), issue 156, July 2010.


Brazil: Angra 3 To Cost US$ 550 million more.
The overall budget for the construction of the Angra 3 nuclear power plant in Brazil will be around R$ 9.9 billion (US$ 5.06 billion or 4.03 billion euro), according to the manager of Planning and Budgeting of Eletronuclear, Roberto Travassos. The increase of more than R$ 1 billion (US$ 550 million or 438 million euro) over the previous estimate (R$ 8.77 billion/ US$ 4.875 billion), is the result of contract  revisions and monetary correction of former estimates.
Global Energy (Brazil), 1 July 2010


Outgoing UN Inspector: dubious role on Iran.
Olli Heinonen, the Finnish nuclear engineer who resigned July 1, after five years as deputy director for safeguards of the International Atomic Energy Agency (IAEA), was the driving force in turning that agency into a mechanism to support U.N. Security Council sanctions against Iran. Heinonen was instrumental in making a collection of intelligence documents showing a purported Iranian nuclear weapons research program the central focus of the IAEA’s work on Iran. The result was to shift opinion among Western publics to the view that Iran had been pursuing a covert nuclear weapons program. But his embrace of the intelligence documents provoked a fierce political struggle within the Secretariat of the IAEA, because other officials believed the documents were fraudulent.

Heinonen took over the Safeguards Department in July 2005 – the same month that the George W. Bush administration first briefed top IAEA officials on the intelligence collection. The documents portrayed a purported nuclear weapons research program, originally called the "Green Salt" project, that included efforts to redesign the nosecone of the Shahab-3 missile, high explosives apparently for the purpose of triggering a nuclear weapon and designs for a uranium conversion facility. Later the IAEA referred to the purported Iranian activities simply as the "alleged studies." The Bush administration was pushing the IAEA to use the documents to accuse Iran of having had a covert nuclear weapons program The administration was determined to ensure that the IAEA Governing Board would support referring Iran to the U.N. Security Council for action on sanctions, as part of a larger strategy to force Iran to abandon its uranium enrichment program.

Long-time IAEA Director-General Mohammed ElBaradei and other officials involved in investigating and reporting on Iran’s nuclear program were immediately skeptical about the authenticity of the documents. According to two Israeli authors, Yossi Melman and Meir Javadanfar, several IAEA officials told them in interviews in 2005 and 2006 that senior officials of the agency believed the documents had been "fabricated by a Western intelligence organizations." Heinonen, on the other hand, supported the strategy of exploiting the documents to put Iran on the defensive. His approach was not to claim that the documents’ authenticity had been proven but to shift the burden of proof to Iran, demanding that it provide concrete evidence that it had not carried out the activities portrayed in the documents.
Gareth Porter at Antiwar.com, 2 July 2010


U.K.: Waste costs 'not acceptable' for industry.
The nuclear industry has been heavily lobbying to change proposed charges for managing wastes from nuclear reactors. Papers released under Freedom of Information show how the French company EDF pressed the previous government to change the proposed 'high fixed cost' for managing wastes and the timetable for handing the management of wastes to the Nuclear Decommissioning Authority. The previous government made significant changes to the way it initially proposed charging companies for managing their wastes. It also agreed that responsibility for wastes should pass to the NDA after 60 years instead of the original 110 years. This would reduce the financial liabilities and costs for companies.

EDF told the government the original proposals were "non-acceptable" and made it uneconomic to develop new reactors.
N-Base Briefing 665, 9 June 2010

In brief

Nuclear Monitor Issue: 
#712
18/06/2010
Shorts

Russia to invest heavily in Namibia.
Russia is ready to invest US$1-billion in uranium exploration in Namibia. "We're ready to start investing already this year," the head of state corporation Rosatom, Sergei Kiriyenko, told journalists. Rosatom seeks to compete for projects with global miner Rio Tinto in the African country. Earlier in May, Russia and Turkey signed a US$20-billion project for Moscow to build and own a controlling stake in Turkey's first nuclear power plant.

Namibia, the world's fourth-largest uranium producer, is home to the Rossing mine operated by Rio Tinto, which together with Paladin Energy's Langer Heinrich mine accounts for about 10% of global output. Other firms have been joining the exploration drive, with several new mines due to come on stream in the next five years.

Although Russia plans to spent a lot of money on foreign nuclear projects, it is clear that there is not enough money to realize its domestic nuclear program. As described in Nuclear Monitor 707 the number of reactors planned to be built by 2015 will be cut by 60%. And even that number will be hard to build.
Reuters, 20 May 2010


UK: Decommissioning black hole.
The new U.K. Government will have to find an extra £4 billion for decommissioning and waste management at the UK civil nuclear. Energy minister Chris Huhne said: "as you can imagine, this is a fairly existential problem. The costs are such that my department is not so much the department of energy and climate change, as the department of nuclear legacy and bits of other things." He added that there were "genuine safety issues" so the costs could not be avoided. As a result, the Government is considering extending  the life of some of the UK's oldest reactors as a way of raising extra income for decommissioning. Extending the life of the reactors owned by the NDA would raise extra income. The Wylfa reactor on Anglesey, for example, is due to close at the end of the year, but extending its operating life for another two years would mean £ 500 million (US$ 736 million or 598 million euro) in new revenue. The NDA is also considering extending the life of the Oldbury reactor, first opened in 1968. Any application to extend the life of reactors would have to be approved by safety regulators.
N-Base Briefing, 9 and 16 June 2010


France: Subcontractors not in epidemiological surveys.
French antinuclear network 'Sortir du nucléaire' supports nuclear industry subcontractor and whistleblower Philippe Billard. As a spokesperson of the organisation 'Santé / Sous-traitance' (“Health and Subcontracting”), he has undergone some retaliation measures after having denounced workers exposure to radiation. As a  whistleblower, he’s now treated as persona non grata in nuclear power  plants. His employer refuses to re-instate him at his previous job, in  contradiction with the Labour Inspectorate’s recommendations.

The French antinuclear network “Sortir du nucléaire”, considers Philippe Billard’s ousting as a means to put pressure on whistleblower workers. “Sortir du nucléaire”  decided to bring its support to the workers who, just like Philippe Billard, suffer from the unbearable working conditions imposed by the nuclear industry and undergo irradiation without even receiving appropriate health care.

To protect its corporate image, EDF chose to give subcontractors the most dangerous tasks. These people working in the shadows have insecure jobs and are mostly temporary and/or nomad workers. Every year, 25,000 to 30,000 of them are made to carry out tasks where they are exposed to radiations. This system allows EDF to cover up a huge health scandal, since these subcontractors, who get 80% of the annual collective dose from the whole French nuclear park, are not taken into account in epidemiological surveys! (See: Annie Thébaud-Mony, « L’industrie nucléaire organise le non-suivi médical des travailleurs les plus exposés », Imagine, May-June 2007)

EDF is shamelessly multiplying talks on transparency while hushing up workers whistle blowing about the imminent catastrophe. In the ageing French nuclear park, the accident risk is increasing, all the more since maintenance periods are shortened in order to save time and money. However, the official motto remains “Nothing to report” and short-term profits are more important than common safety and security.
Press release 'Sortir du nucleaire', 31 May 2010


Switzerland: Thousands march against nuclear power.
More than 5,000 people gathered in Goesgen, canton Solothurn, in northern Switzerland on May 24, for a peaceful protest against the continuing development of nuclear energy in the country. The protest had participants from 83 groups in Switzerland, France, Germany and Austria. One of their key points was that Switzerland’s nuclear power plans are preventing the rapid development of alternative energy programs. The demonstration was one of the largest in last years.
www.menschenstrom.ch


Another subsidy for Areva in the U.S.
"As part of a broad effort to expand the use of nuclear power in the United States and reduce carbon pollution," the U.S. Department of Energy has approved a US$2 billion loan guarantee for French nuclear power developer Areva S.A. (owned for about 93 percent by the French State). The loan guarantee will support Areva's Eagle Rock Enrichment Facility near Idaho Falls, Idaho, which will supply uranium enrichment services for the U.S. nuclear power industry. Areva's US$3.3 billion nuclear enrichment facility will use centrifuge technology instead of gaseous diffusion technology that is more common in the U.S. but uses more energy. Areva had filed its application for the guarantee with the Department of Energy in September 2008.

The group can tap the guarantee once its Idaho Falls project has received full approval by the authorities. The Nuclear Regulatory Commission is expected to decide sometime next year on a licence for the facility. Areva plans to have the plant in operation in 2014. 

The United Stated Enrichment Corporation (USEC) is also seeking a loan guarantee for its American Centrifuge Project under development at Piketon, Ohio. Following DOE's announcement the consensus would seem to be that 'd be bad news for USEC. But according to USEC spokesman Paul Jacobson that is not the case. Jacobson said USEC was encouraged that DOE recognizes the need for more enrichment services to supply the nuclear needs of the future. He also noted that DOE, as noted in the federal agency's press release, still has another US$2 billion in loan authority available. At one time, USEC was going head to head with Areva for the loan guarantees, and USEC played up the foreign-owned company versus domestic company, etc., but now the company -- on the public front at least -- seems to be focused on the nuclear renaissance and the idea that there's enough demand in the U.S. and abroad to support multiple new ventures in the enrichment arena.
U.S. DOE, 20 May 2010 / Reuters, 20 May 2010 / Atomic City Underground, 21 May 2010


EC: investigation non-compete clauses Areva, Siemens.
The European Commission has opened an antitrust case to determine whether non-compete clauses in civil nuclear technology arrangements between Areva of France and Germany's Siemens violate EU competition rules. The opening of antitrust proceedings on June 2, means that the EC thinks the case merits investigation. EC competition spokeswoman Amelia Torres said an investigation was triggered by a complaint from Siemens after Areva took full control last year of reactor construction and services company Areva NP, a joint venture originally set up by Framatome (which later became Areva) and Siemens in 2001. But non-compete clauses between the two companies remain, even though Siemens sold its 34% stake to Areva last year.

The shareholders' pact between Areva and Siemens for Areva NP is not public, but a French official familiar with it confirmed that it forbids either party from competing with the other in businesses covered by Areva NP for eight years after a potential divorce.

Siemens said in January 2009 that it intended to exercise its option, to sell its 34% stake in Areva NP to Areva and leave the joint venture. A few weeks later, Siemens said it had signed a memorandum of understanding on a nuclear power business partnership with Rosatom, a Russian state-owned nuclear conglomerate. After bilateral discussions failed to produce an agreement on the price at which Areva would buy the 34% stake in Areva NP, the erstwhile partners last year asked an arbitration court to decide the matter.

EC competition spokeswoman Amelia Torres said the investigation would be carried out by the EC at EU-level, rather than by national governments. There is no timescale for the investigation as this depends on the complexity of the case and the extent to which the parties cooperate. Torres said she was not able to prejudge whether a fine would be imposed if the arrangement were found to be in breach of competition rules.
Platts, 2 June 2010


U.K.: Waste costs 'not acceptable' for industry.
The nuclear industry has been heavily lobbying to change proposed charges for managing wastes from nuclear reactors. Papers released under Freedom of Information show how the French company EDF pressed the previous government to change the proposed 'high fixed cost' for managing wastes and the timetable for handing the management of wastes to the Nuclear Decommissioning Authority. The previous government made significant changes to the way it proposed changing companies for managing their wastes. It also agreed that responsibility for wastes should pass to the NDA after 60 years instead of the original 110 years. This would reduce the financial liabilities and costs for companies.

EDF told the government the original proposals were "non-acceptable" and made it uneconomic to develop new reactors.
N-Base Briefing 665, 9 June 2010


Chubu delays Hamaoka-5 restart after earthquake.
Japan: The Chubu Electric Power Company has extended the closure of its 1,380-megawatt Hamaoka No.5 reactor by a further two months to the end of July. Chubu Electric said the decision had been taken because the company is still analyzing why the impact of the August 11, 2009 earthquake on the reactor was greater than for other nuclear units. The company explained that, based on this measure of earthquake ground motion, the impact of the tremor was significantly higher than for other reactors. Chubu Electric will report its findings to the Ministry of Economy, Trade and Industry. It hopes to restart the reactor after METI and other government  agencies have agreed the report and local communities have consented to the restart of the reactor. The restart of the No. 5 reactor was originally planned for the end of December 2009, but pushed back several times.
Power in Asia 555,  27 May 2010


Bangladesh: cooperation agreement with Russia.
The government of Bagladesh has increased momentum for the installation of the country’s first nuclear power plant. The US$1.5-billion project will be built at Rooppur, about 300 kilometers from the capital Dhaka. A committee headed by the state minister for science and information and communication technology, Yafes Osman, has been constituted to implement the project. The 22-member committee, which has the chairman of the Bangladesh Atomic Energy Commission as its member secretary, will examine funding issues and assess the risks associated with the fiscal arrangements. It will also study nuclear waste management issues. Bangladesh plans to install the 2,000-megawatt plant (for US$1.5billion?) at Rooppur from 2017. It signed a five-year framework cooperation agreement with the Russian atomic energy company Rosatom in May, with the final agreement due to be signed during Prime Minister Sheikh Hasina’s visit to Moscow later in 2010.
Power in Asia 555, 10 June 2010


Go-ahead for Urenco's Eunice plant.
The US Nuclear Regulatory Commission (NRC) has authorized the operation of the first cascade at Urenco's Louisiana Energy Services (LES) gas centrifuge enrichment plant at Eunice, New Mexico. LES is a wholly owned subsidiary of URENCO Ltd. Urenco said the process to bring the plant from construction status to fully operational will begin later in June. The Urenco USA plant (formerly the National Enrichment Facility)  will be the first commercial centrifuge enrichment plant to become operational in the USA. Urenco formally inaugurated the plant in early June. "At full capacity, the facility will produce sufficient enriched uranium for nuclear fuel to supply approximately 10% of the electricity needs for the US", according to the Urenco press release.
Urenco Press release, 11 June 2010

In brief

Nuclear Monitor Issue: 
#708
29/04/2010
Shorts

Finland: building nukes for electricity export?
On April 21, the Finnish government proposed two new nuclear power plants. The parliament will make the final decision on the issue earliest in the summer, but most likely in the autumn. On both reactors will be voted separately - there are possibilities to have 2, 1 or 0 new nuclear plants. Building twe nuclear power units would lock Finland's energy consumption to unrealistic, artificially high levels, and are clearly aimed for electricity export. However, Parliament has taken the line that it opposes the construction of generating capacity for export purposes.

Minister of Economic Affairs Mauri Pekkarinen (Centre Party) insisted on April 21, that Finland would adhere to this principle of opposing the construction for export. But the Greens are accusing Pekkarinen of turning his coat on the matter by endorsing two new reactors just a year after saying that Finland’s need for new nuclear energy units was “zero, or one at the most”. “Now he is proposing two units on the basis of the same electricity consumption estimates. This certainly shows how poorly founded Pekkarinen’s proposal is”, Sinnemäki says. The Greens also point out that the forest company UPM, a part owner of TVO, has put forward the idea of electricity exports. “Nobody in Finland -not even the forest industry- has proposed such a fantasy in electricity production that this proposal would not mean export. It becomes clear even in all of the most daring consumption estimates. We simply cannot consume this much electricity.”

Environmental organisations are organizing a large anti-nuclear demonstration in Helsinki on May 8.
Helsingin Sanomat (Int. edition) 22 and 24 April 2010


Japan: Restart Monju expected in May.
The Monju prototype fast-breeder reactor, which was shut down in December 1995 after sodium leaked from the cooling system, is set to resume operations in May.  Fukui Governor Issei Nishikawa signaled his willingness to approve reactivation of the experimental reactor, located in Tsuruga, Fukui Prefecture, during a meeting with science and technology minister Tatsuo Kawabata and industry minister Masayuki Naoshima on April 26. In the 1995 incident, the reactor operator was heavily criticized after it was found to have concealed information about the accident. During the past 14 years or so that Monju has been in limbo, the operator has come under fire for delaying reports on alarm activation incidents and flawed maintenance work.

Under the government's plan, the next stage in the fast-breeder project will be the construction of a demonstration reactor, which is larger than Monju, around 2025. It would be followed by the development of a commercial reactor around 2050. But the outlook for the plan is bleak, to say the least.

Some 900 billion yen (US$ 9.6 billion or 7.3 billion euro) of taxpayer money has already been spent on the construction and operation of the Monju reactor. It will require additional annual spending of about 20 billion yen (US$ 215 million / 162 million euro).

More on the history and current status of Monju and Japan's fast breeder programm: Nuclear Monitor 702, 15 January 2010: "Restarting Monju – Like playing Russian roulette"
The Asahi Shimbun (Japan), 27 April 2010


Belene contruction halted until investors are found.
Belene construction was halted in search for Western strategic investors after Bulgaria dismissed an offer from Russia to finance the coming two years of construction with an option for a complete Russian take-over of the project. The Bulgarian government has opened a tender for a financial consultant to work out a new financial model for the project. This consultant is expected to be chosen in June 2010. On the basis of this new financial model, strategic investors will be invited for participation. After EU Energy Commissioner Günther Öttinger warned Bulgaria for the dependency that a fully Russian Belene project would create, Bulgarian Prime Minister Boyko Borrisov made it clear that Belene only will be continued if it can pay for itself and if it is developed under participation of European and/or US partners. Russia was not to expect more than a 25% participation, if any at all. In his straightforward way, Borissov characterised Belene as either a  European project or no project.

On 16 April, it was also announced that the Bulgarian Energy Holding, which was set up in 2008 to create a pool of assets that could lure possible lenders to the Belene project, will be dismantled before summer. Deputy Minister for Economy, Energy and Tourism Maya Hristova said that BEH was set up to the secure the construction of Belene by the assets generated in the holding, "but this is no longer feasible." She told the Bulgarian press agency BTA that the assets of all state-owned energy companies are of lower value than the estimated value of  Belene. Daily Dnevnik announced that there is currently a discussion to bring the electricity  assets of BEH, including the Kozloduy nuclear power plant and the Maritsa East power station under in state utility NEK and the gas assets in a seperate holding.
Email Jan Haverkamp, Greenpeace EU Unit, 26 April 2010


U-price low: "explosive growth in nuclear power hasn't yet happened". 
The spot price of uranium has dropped below US$42/lb (1 lb = 453.59 grams) through in April, down almost US$4 from the 2009 average of US$46 as, according to Purchasing.com, weakening demand has depressed transaction pricing. Lyndon Fagan, an analyst at RBS in Sydney Australia, tells Bloomberg that spot prices indeed have weakened in recent months because the explosive growth in nuclear power hasn't yet happened. Current uranium prices are well down from the levels reached in 2007, when the prices spiked to nearly US$140. Supply concerns drove the price up at that time, and while there's no guarantee that prices could once again reach those levels, such past performance does imply that the potential for such dramatic price moves is possible.

Meanwhile, Admir Adnani, CEO of US-based UraniumEnergy, tells Reuters that a renewed focus on nuclear energy and current mining shortfalls are likely to drive prices of uranium, higher in the coming years. "In the next two to three years, we will see a period of rising uranium prices," Adnani says. "There is absolutely no doubt that the nuclear renaissance and the construction of new reactors plus the existing reactor requirements will bring growing demand... and we need uranium prices to be higher for new mines to be built." But in the Canadian province of New Brunswick, for instance, only two companies have done exploration work over the past couple years, a notable drop from the 10 or so firms that were searching for uranium back in 2007, according to the Canadian Department of 

Natural Resources. www.purchasing.com, 14 April 2010 / Telegraph Journal (Canada), 21 April 2010


Regulators investigating Olkiluoto piping.
Nuclear safety authorities in Finland, France, the UK and US are assessing the significance of undocumented welding on primary circuit piping for the EPR reactor under construction at Olkiluoto, Finland. However, Petteri Tiippana, director of the nuclear reactor regulation department at the Finnish Radiation and Nuclear Safety Authority STUK, told Platts in an interview on April 8, that regulators from those four countries are not preparing a joint statement on the piping quality issue. He reacted on a statement made by a commissioner of French nuclear safety authority ASN,

The piping was manufactured by Nordon, a subcontractor to Areva, the French vendor which is supplying the nuclear part of the Olkiluoto-3 unit under a turnkey contract to utility Teollisuuden Voima Oy. Nordon, based in Nancy in eastern France, is a unit of the Fives group and has long been a major supplier of piping for nuclear power plants. In October 2009, STUK found that small cracks in piping made for the main coolant lines of Olkiluoto-3 had been repaired with welding procedures that were not documented. Tiippana said the piping is still in France and that analysis of the significance of the undocumented welding could be finished within several weeks. STUK will then do final inspections, probably before summer, he said. Until the piping is approved by STUK, it cannot be transported to Olkiluoto.The design of Areva's EPR reactor is under regulatory review for construction in the UK and the US.
Platts, 8 April 2010


Australian uranium for India?
Not that long ago, Australia took a firm stand against selling uranium to India (or any Non-Nuclear proliefration Treaty signatory for that matter): in January 2008, Australia’s new Labor government outlawed uranium sales to India. Stephen Smith, Australian foreign minister emphasizes that in saying in October 2009: “We have had a long-standing principal position which is not aimed at India, it is the long-standing position that we do not export uranium to a country that is not a party to the Nuclear Non-Proliferation Treaty,”

Now, just over a half year later, Australia is planning to change its domestic rules to allow India to import uranium from the country.

India is signing the Indo-US civilian nuclear agreement and many other civil nuclear agreements with different countries. The 46-member Nuclear Suppliers Group (NSG) has also granted a waiver to India in September 2008 allowing nuclear fuel from other nations. However, Australia being a member in that group, didn’t allow India to import nuclear fuel from the country. Now, South Australia’s Department of trade & economic development director Damian Papps said Australia would like to amend the current regulations to enable uranium export to India.
Press TV, 14 October 2009 / Spectrum, April 26, 2010


Further increase heavy forging capacity.
Known as a leader in the ultra-heavy forgings required for the highest capacity nuclear reactors, Japan Steel Works set about tripling its capacity and has completed its second press for ultra-large nuclear forgings. It has now completed the ¥50 billion (US$530 million, 390 million euro) first phase of the expansion with the installation of a new forging shop complete with heavy cranes, heat treatment facilities and the necessary 14,000 ton press.

JSW told World Nuclear News that the new shop was the core of the first investment phase and that the second ¥30 billion (US$320 million, 235 million euro) investment round should be completed in 2011. At that point, JSW said, it would have tripled the nuclear capability that it had in 2007 - enough for about 12 reactor pressure vessels and main component sets per year. The increase in capacity should be felt by mid-2012 as new components are planned to emerge from the factories. Muroran also manufactures generator and steam turbine rotor shafts, clad steel plates and turbine casings for nuclear power plants.

While JSW may be the current leader in the global market for large nuclear components, there are several other (Russian, Chinese and South-Korean) manufacturers tooling up to the same levels for domestic supply. Britain's Sheffield Forgemasters and India's Bharat Forge will join JSW as global ultra-heavy suppliers around 2014.
World Nuclear News, 1 April 2010


Switzerland: Canton slams radioactive waste plans.
Plans for a radioactive waste disposal unit in the canton of Schaffhausen has come under fire in a study published by the local government. The National Cooperative for the Disposal of Radioactive Waste outlined two possible sites for the unit: one in Zurich Weinland and one near Sudranden in the canton of Schaffhasusen. That’s just a few kilometers from the city of Schaffhausen, where 80 percent of the canton’s population live and work. The report published on April 21 says a disposal centre would have a detrimental effect on the town of Schaffhausen, and on the development of both the canton’s economy and population. The report estimates it would lose between 15 and 33 million francs in tax revenue a year and the population would drop by up to 5,000 people.
World Radio Switzerland, 21 April 2010


U.K.: Low-level radwaste in a landfill.
Five bags of radioactive waste from the Sellafield nuclear processing facility were dumped in a landfill site after a faulty scanner wrongly passed them as safe. Environment Agency inspectors have found one of the bags but is still searching for the other four at the Lillyhall landfill site near Workington, Cumbria. The bags contained waste collected in restricted areas of Sellafield where disposal of all items, including protective clothing, is strictly controlled because of the risk of radioactive contamination. The error was discovered by a member of staff who became suspicious when a scanning machine declared as safe a bag that had come from the restricted area. Staff checked the machine's records and found that five other contaminated bags had been passed as safe and sent to the nearby landfill site, which handles a mixture of household and industrial waste. A Sellafield spokeswoman was unable to say for how long the machine had been malfunctioning. The waste should have been sent for storage in concrete vaults at the Low Level Waste Repository near Drigg in Cumbria.

The incident may undermine the nuclear industry's plan to save billions of pounds by adopting lower safety standards for thousands of tonnes of low-level radioactive waste from decommissioned reactor sites. Several landfill sites have applied for permits to handle low-level waste.
Times online (U.K.), 26 April 2010


U.K. political parties and nukes.
The political party manifestos for the General Election show no surprises concerning nuclear policies - and they reveal the fundamental difference on nuclear issues between the Liberal Democrats and both the other two main parties. These difference will make for some tough bargaining in the event of a hung Parliament in which no political party has an outright majority of seats.

The Conservatives commit themselves to "clearing the way for new nuclear power stations - provided they receive no public subsidy". The party is also committed to the new Trident nuclear submarine system.

Under the heading 'Clean Energy' the Labour manifesto says "We have taken the decisions to enable a new generation of nuclear power stations" and the party is also committed to the Trident replacement.

The Scottish National Party wants Trident scrapped, rejects nuclear energy and the deep geological disposal of radioactive wastes.

The Liberal Democrats don't want a "like-for-like" replacement for Trident and promise a review of the proposals. They also reject new reactors "based on the evidence nuclear is a far more expensive way of reducing carbon emissions" than renewable energy and energy conservationAccording to the LibDem spokesperson on energy and climate issues, Simon Hughes, the curent government plans for a new fleet of nuclear reactors are based on a "completely foolish delusion". And he added; "they are too costly, wil take too long to build, will require government subsidy and will drain investment away from the renewable energy sector".  He says the party will not soften anti-nuclear stance.

General elections in the UK will be held on May 6.
N-Base Briefing 649, 21 April 2010 / BusinessGreen.com, 26 April 2010


Rand Uranium: no super dump tailings in Poortjie area.
South-Africa: following a successful protest march on April 23 by emerging black farmers and the Mhatammoho Agricultural Union, and the potentially affected landowners against the proposed super dump (centralized tailings storage facility -TSF) Rand Uranium decided to abandon the project. The protest march, the second in a few weeks, took place at the offices of Rand Uranium in Randfontein. Soon after the protest, Rand Uranium, which had proposed to establish the TSF within the Poortjie area on high agricultural land, issued a statement. The last paragraph of the document reads:  "Through the assessments, and in consideration of planning requirements of the City of Johannesburg, Area 45 is not considered appropriate for the long term TSF." The protest was against Site 45 (Poortjie area).  This means, Rand Uranium has abandoned its intention to establish a super dump in the Poortjie area. 

The proposed super dump would contain 350 million tons of uraniferous tailings and will be established on 1 200 hectares of land. The farmers and landowners claim that the public participation process was fatally flawed and that they were not consulted. It would have impacted the Vaal Barrage Catchment, a highly compromised Catchment. In terms of the Water Research Report No 1297/1/07 (2007) only 21% of the Vaal Barrage showed no evidence of cytotoxicy (i.e. toxic to human cells).  The Report suggests that the underlying problems of this catchment are largely due to heavy metals.  It furthermore states:  "It is clear that mining operations, even after they have been discontinued, are still having a major impact on water quality in the Vaal Barrage catchment, to the extent that it can no longer be compared with other natural water systems."
Emails Mariette Liefferink, 21 and 24 April 2010


U.A.E.: First nuclear site named. Braka has been named as the site for the United Arab Emirate's first nuclear power plant. Limited construction licence applications and environmental assessments for four reactors have been submitted.
The Braka site is in a very sparsely populated area 53 kilometers from Ruwais and very close to the border with Saudi Arabia. It is closer to Doha, the capital of Qatar, than to Abu Dhabi about 240 kilometers to the east. Dubai is another 150 kilometers along the coast. The Emirates Nuclear Energy Corporation (Enec) said Braka was selected from ten shortlisted sites, all of which were suitable for nuclear build, on the basis of its environmental, technical and business qualities.

Two requests have been made to the Federal Authority for Nuclear Regulation (FANR). One is for a site preparation licence for the four-reactor power plant to allow Enec to conduct non-safety related groundwork at Braka such as constructing breakwaters and a jetty. The other is for a limited licence to "manufacture and assemble nuclear safety related equipment."  In addition, a strategic environmental assessment for the project has been submitted to the Environment Agency - Abu Dhabi (EAD) addressing environmental impacts and mitigation including for construction work.

But since there is no civil society whatsoever, there will be no independent scrutiny of those documents.
World Nuclear News, 23 April 2010


Contract for ITER buldings.
The Engage consortium has been awarded the architect engineer contract for the International Thermonuclear Experimental Reactor (ITER) buildings and civil infrastructures. The contract, worth some €150 million (US$200 million), was signed by the Engage consortium and Fusion for Energy (F4E) on 13 April. F4E is the European Union's (EU's) organization for Europe's contribution to ITER. The Engage consortium comprises Atkins of the UK, French companies Assystem and Iosis, and Empresarios Agrupados of Spain. The architect engineer will assist F4E during the entire construction process, from the elaboration of the detailed design to the final acceptance of the works. The contract covers the construction of the entire ITER complex, including 29 out of a total of 39 buildings, site infrastructure and power supplies.

Seven parties - China, India, Japan, Russia, South Korea and the EU - are cooperating to build ITER, a 500 MWt tokamak, at Cadarache. The partners agreed in mid 2005 to site Iter at Cadarache. The deal involved major concessions to Japan, which had put forward Rokkasho as a preferred site. The EU and France will contribute half of the €12.8 billion (US$18.7 billion) total cost, with the other partners - Japan, China, South Korea, USA and Russia - putting in 10% each. Site preparation at Cadarache began in January 2007. The facility is expected to be in operation around 2018. As part of the reactor's phased commissioning, it will initially be tested using hydrogen. Experiments using tritium and deuterium as fuel will begin in 2026. Much later than expected a few years ago.
World Nuclear News, 15 April 2010

In brief

Nuclear Monitor Issue: 
#705
12/03/2010
Shorts

RWE looses again: Borssele has to remain in public hands.

RWE failed to gain 50% of the Netherlands' only nuclear power plant at Borssele through its takeover of Dutch utility Essent. The ruling by the Arnhem appeal court upholds an earlier ruling prohibiting Germany's RWE from acquiring Essent's 50% stake in the Borssele nuclear plant as part of its takeover of the Dutch utility. According to Delta, the appeal court decision has emphasized that the country's sole nuclear power plant must remain in public ownership. Any transfer of Essent's share of the plant to RWE would therefore contravene this. In September 2009, the transaction price for RWE's takeover of Essent was dropped by 950 million Euro (then worth US$1.35 billion) to take into account the exclusion of Borssele from the deal while Delta's court case against the proposed transfer was ongoing. Essent's share in the plant has remained in the hands of the provincial and municipal governments who were the company's original public shareholders.
The Dutch coalition government collapsed on February 20, when the two largest parties failed to agree on whether to withdraw troops from Afghanistan this year as planned. Elections are planned on June 9, with an expected right-wing victory. The extreme-right party PVV ('party for freedom') is expected to become one of the largest –or even the largest- party in parliament. The PVV is (besides anti-islam and with racist tendencies) extremely pro-nuclear, anti-wind & solar energy and does not believe in climate change ands speaks consistently about the environmental movement as the 'environmental maffia'.

The just fallen coalition government had agreed not to approve any new nuclear plants in the Netherlands during its mandate. Dutch utility Delta has announced plans to build a second nuclear plant at the site, embarking on the first stage of the pre-application process in June 2009.

German utility RWE has indicated it is also interested in building a nuclear power plant in the Netherlands, RWE CEO Juergen Grossmann said at the company's annual earnings press conference on February 25 in Essen, Germany

World Nuclear News, 3 March 2010 / Platts, 25 february 2010


USDOE: US$40 million for Next Generation Nuclear Plant.

On March 8, U.S. Secretary of Energy Steven Chu announced selections for the award of approximately US$40 million in total to two teams led by Westinghouse Electric Co. and General Atomics for conceptual design and planning work for the Next Generation Nuclear Plant (NGNP).  The results of this work will help the Administration determine whether to proceed with detailed efforts toward construction and demonstration of the NGNP.  If successful, the NGNP Demonstration Project will demonstrate high-temperature gas-cooled reactor technology that will be capable of producing electricity as well as process heat for industrial applications and will be configured for low technical and safety risk with highly reliable operations.  Final cost-shared awards are subject to the negotiation of acceptable terms and conditions.

The NGNP project is being conducted in two phases.  Phase 1 comprises research and development, conceptual design and development of licensing requirements. The selections announced now will support the development of conceptual designs, cost and schedule estimates for demonstration project completion and a business plan for integrating Phase 2 activities. Phase 2 would entail detailed design, license review and construction of a demonstration plant.

U.S. Department Of Energy, Press Release 8 March 2010


Switzerland: Geneva will fight extension Muhleberg licence.

Geneva City Council has decided to appeal to the Federal Administrative Tribunal against the decision of the federal authorities to allow the 355 MW Mühleberg nuclear plant to continue operating beyond 2012, when it will have been 40 years in service. Geneva will contribute CHF 25,000 (US$23,000 or 17,000 Euro) to help meet the costs of a committee formed to oppose the licence extension. In November 2009 the electorate of the neighbouring canton of Vaud also voted against the extension. The centre-left Social Democrats and the Green Party are also opposing the licence extension.

Power In Europe, 22 February 2010 / Nuclear Monitor 702, 15 January 2010


Uranium mining - victory in Slovakia!

After more than three years of campaigning Slovak parliament finally agreed on legal changes in geological and mining laws in order to stop uranium mining in Slovakia. All the changes were proposed by anti-uranium mining coalition of NGOs led by Greenpeace and supported by over 113 000 people that signed the petition.  For Slovak environmental movement this is a really important milestone. For the first time in Slovak history NGO’s were able to:

1) collect over 100 000 signatures (a number given by law for the Parliament to discuss an issue) - note that Slovakia has 5 million citizens; 2) to open an environmental topic in Slovak parliament by a petition; 3) and finally to achieve a legal change by petition  initiative.

Legal changes agreed by parliament on March 3 are giving more information access and competencies for local communities, municipal and regional authorities to stop or limit geological research of uranium deposits and to stop proposed uranium mining. It’s not a complete ban of uranium mining, but a significant empower of local and regional authorities in the mining permitting process. All 41 municipal authorities influenced by proposed uranium mining already declared that they do not agree with proposed uranium mining in their territories.

The chance that Slovak uranium will stay deep in the ground is much higher today!

Greenpeace Slovensko, Bratislava, 4 March 2010


Uranium from stable and democratic countries?

One of Kazakhstan's most prominent business figures and a former uranium tycoon, Mukhtar Dzhakishev was arrested last year on accusations of corruption, theft and illegal sales of uranium assets to foreign companies. Dzhakishev's case, along with a string of other high-profile arrests in the former Soviet state and world No. 1 uranium producer, has fuelled speculation of an intensifying power struggle within the political elite.

Kazakhstan, hit hard by global economic slowdown, wants to attract fresh foreign investment as well as bolster the role of the state in strategic industries such as uranium and oil. It has also alarmed human rights groups who have questioned Kazakhstan's methods of fighting corruption in a country where President Nursultan Nazarbayev, in power for two decades, tolerates little political dissent.

Dzhakishev, who was head of state uranium major Kazatomprom from 1998 until his arrest and played a key role in turning Kazatomprom into a major global uranium player, has denied all accusations. "It is obvious that I cannot count on justice in my own country and my fate has already been decided," he wrote from his detention centre in a letter published by his lawyers this week. His arrest left Kazatomprom's foreign partners such as Canada's Uranium One worried about the future of their projects. Other investors include France's Areva and Japanese companies such as Toshiba Corporation. Closed-door court hearings into earlier allegations of theft and corruption have already started and lawyers expect a verdict in March.

Reuters, 4 March 2010


Israel to build reactor –but will not allow inspections?

Israel will shortly unveil plans to produce nuclear-generated electricity, officials said on March 8. Infrastructure Minister Uzi Landau said Israel, which has a population of 7.5 million and generates electricity mostly using imported coal and local and imported natural gas, is capable of building a nuclear reactor, but it would prefer to work with other countries. Israel already has two reactors -- the secretive Dimona facility in the Negev desert, where it is widely assumed to have produced nuclear weapons, and a research reactor, open to international inspection, at Nahal Soreq near Tel Aviv.

Unlike other countries in the region, Israel has not signed the 1970 Non-Proliferation Treaty (NPT), which is suppose to curb the spread of nuclear technologies with bomb-making potential. Yet Israel does have a delegation at the International Atomic Energy Agency (IAEA). Landau said it would not be a problem for Israel to build a civilian reactor without signing the NPT: "There are many countries who are not signatories to the NPT and they are doing fine. There are others which are signatories and the world community did not really take proper care against proliferation," he said. Many countries? India, Pakistan and North-Korea (withdrawn), three (excuse me, four with Israel) and 189 signatories, you call that many? Asked whether IAEA inspectors would supervise the building of an Israeli plant, Landau said: "We take care very well of our own needs and don't need inspectors."

Reuters, 8 March 2010

…. And Syria? (March 11, 2010) Meanwhile, Israels' arch-foe Syria responded in Paris saying that Damascus needs "to consider alternative sources of energy, including nuclear energy." Syria's candidacy for the nuclear club will raise some eyebrows too, given the regime's close ties with Iran and the still unanswered questions over an earlier alleged attempt to build a reactor in secret. The International Atomic Energy Agency complained last year that Damascus had refused to cooperate with its investigation of a remote desert site called Dair Alzour, which was bombed by Israel in September 2007. Inspectors have found unexplained traces of uranium at the site, as well as at a nuclear research reactor in Damascus, amid reports that Syria has been working with Tehran and North Korea on covert nuclear programs.

AFP, 9 March 2010


Winter meeting of the Nuclear Heritage Network.

This relatively new network has been very active against uranium mining in Finland and is currently organising a Baltic Sea Info Tour (see http://www.greenkids.de/europas-atomerbe/index.php/Action:Infotour_Aroun...) and preparing new actions against nuclear new-build in the north-east region of Europe .

Their winter meeting will take place from March 24 to 29 in and close by Helsinki, Finland. This includes one day of action, aimed at the to be taken Finnish political decisions on more new nuclear power stations. An important project to be discussed for the summer will be the „Baltic Sea Info Tour“ that will take place to inform people around the Baltic Sea.

More information? Write an email to contact@nuclear-heritage.net


Chernobyl-Day: concerted action to stop Mochovce 3+4. The Wiener Plattform "Atomkraftfreie Zukunft" (Viennese Platform "Nuclearfree Future") has taken the lead in organising an international action-day on April 26, the anniversary of the Chernobyl disaster, against the construction of Mochovce 3+4 in Slovakia. (more on Mochovce in next issue).

They ask groups to demonstrate in front of Slovak and Italian embassies in as many countries as possible. A small delegation should submit a paper to the respective ambassadors. The paper explains the importance of stopping this dangerous Slovak nuclear power plant and says what the responsible people should do.

If these actions are carried out in numerous cities or capitals it should be effective enough to put pressure on Slovakia and the respective governments.  Please join the campaign and contact atomkraftfreiezukunft@gmx.at


Announcement: Anti Nuclear European Forum (ANEF) on June 24, in Linz, Austria.

ANEF was established 2009 as counter-event to ENEF (European Energy Forum) since ENEF failed to fulfill ENEF´s official objectives and was/is used one-sided as a propaganda instrument for the promotion of nuclear power instead. Within ANEF negative aspects of nuclear energy will be discussed on an international level. ANEF is organized by the Antinuclear Representative of Upper Austria in cooperation with “Antiatom Szene” and “Anti Atom Komitee”. The participation of international NGOs is very important because it needs a strong signal against the nuclear renaissance.

The organizers would like to warmly invite you to participate in ANEF. Please let us know as soon as possible if you, or someone else from your organization, is considering to participate in ANEF by sending an informal email to office@antiatomszene.info. The detailed program will be available soon and will be send to you upon request. Accommodation will be arranged for you.
Further information on ANEF is published on www.anef.info. Learn about ANEF-Resolution here: http://www.anef.info/?q=en. 

IN BRIEF

Nuclear Monitor Issue: 
#702
15/01/2010
Shorts

Non-proven Korean reactors for Middle-East.

A South Korean consortium has beaten French, US and Japanese competition and won a US$20.4 billion contract for developing a civilian nuclear program for the United Arab Emirates. Lead by KEPCO the groups also includes companies as Hyundai Engineering and Construction, Samsung and Doosan Heavy Industries. Korea Nuclear Fuel Co, or KNF, will provide the nuclear fuel while Korea Plant Service and Engineering Co (KPS) will be involved in plant maintenance. Non-Korean companies involved in the Kepco team include Westinghouse of the US and Toshiba of Japan. Kepco is owned by the South Korean government and is the world’s third largest nuclear energy businesses. The other bidders in the year-long process included a consortium of French companies – Areva, Total and GDF Suez – by many seen as the most likely winner of the tender - and a third consortium of US and Japanese companies, including General Electric and Hitachi. Loss of the nuclear reactor contract is a major blow to especially the French nuclear industry. French President Sarkozy has extensively been traveling the Middle East , including the UAE in an attempt to bring new orders back home to the state-owned Areva.

The UAE is hoping to become the first Arab Gulf state to develop a civilian nuclear program and the contract involves the design and construction of four 1,400 megawatt units of the APR1400-type, Generation III units. Design was developed by the Korean nuclear industry under the leadership of Kepco over a period of 10 years beginning 1992. The first of the APR1,400 units, Shin-Kori units 3 and 4, are now under construction, having obtained a construction permit from the Korean regulatory authority. Shin-Kori unit 3 is scheduled to be connected to Korea’s grid by 2013. According to the UAE nuclear safety regulator, the Federal Authority for Nuclear Regulation (FANR), Kepco will construct plants that are essentially the same as the “reference plants,” but supplemented with changes required to adapt to UAE climactic conditions and any specific requirements of the UAE.

The UAE hopes the first of its nuclear units will begin producing electricity to its grid in 2017, with the other three being completed in 2020. In spite of being the world’s third largest oil exporter and home to the world’s fifth largest proven natural gas reserves, the UAE is already a net importer of gas to fuel industries and power stations. Demand for electricity in the UAE is currently about 15 GWe, but is projected to nearly triple in just 12 years. Natural gas is the fuel of choice for peak power and half of base load demand in the UAE. Oil provides the rest. No coal is burned in the UAE for electricity. The heart of the UAE base load energy plan is to swap out the natural gas plants for nuclear energy to power water desalinization and electricity for household and industrial use.

Sources: http://djysrv.blogspot.com/2009/12/south-korea-wins-uae-204-billion.html / Financial Times, 27 December 2009 / Khaleej Times, 28 December 2009

England: Tories: We will not build nuclear power stations if elected.

Political Parties not in the government have to speak out against the ruling parties to show they are in opposition. Sometimes that mechanism has strange consequences. The English Conservative Party is a well known proponent of nuclear power. But since the ruling Labour Party shows some dedication to build nuclear reactors, the Tories, changed position. Well, it seems… Early December, the green adviser of Tory leader David Cameron has thrown more doubt on where the party stands over nuclear power after declaring no new stations would be built under a Tory government. Zac Goldsmith, one of Mr Cameron’s closest advisers on the environment, insisted no new nuclear power stations would be built if the Conservatives were to win the next general election. He said Tory policy “was to give a green light to nuclear power as long as there is no call on the taxpayer, not just in terms of building, but maintenance, security and disposal of waste." His next sentence was a very surprising one: "In the history of nuclear power there has never been a station built without huge use of taxpayers’ subsidy.”

Jamie Reed, Labour member of parliament for Copeland (Cunbria) reacted: “This is not a policy, it is ignorant, confused nonsense and is in effect an anti-nuclear policy. David Cameron is all over the place on nuclear. He has stated that it is a “last resort”. And concluding: "With others I have worked hard to build a cross party consensus and I am saddened by the fact that David Cameron and Zac Goldsmith remain anti nuclear." Well, that has to be seen, but let's hope that is still the case when they win the next elections.

Source: North West Evening Mail (UK), 2 December 2009

Areva confirms Greenpeace’s alarming radiation findings in Niger.

Following Greenpeace’s report of radioactive hotspots in the uranium mining city Akokan in Niger, Areva has confirmed that the radioactivity in the streets of Akokan was unacceptably high. Under pressure from civil society the French nuclear company has taken action to clean up the spots indicated by Greenpeace. “Areva’s reaction supports our call for a comprehensive, transparent and independent environmental assessment of the area,” said Dr. Rianne Teule of Greenpeace International. “We are glad that the streets of Akokan have been partly cleaned up, but remain very concerned that  other problems cannot be ruled out without a comprehensive study. Decades of uranium mining have created radioactive dangers to the people of Akokan, a typical example of environmental and health threats posed by the nuclear industry.”

A Greenpeace team visited Areva’s two uranium mines in Niger at the beginning of November 2009. During this visit Greenpeace identified dangerous levels of radiation in the streets of Akokan, at one location up to 500 times higher than the normal background levels. Areva had earlier declared the streets safe. A comprehensive report on Greenpeace’s findings will be published in early 2010.

Source: Greenpeace International Press release, 5 January 2010

Preparations for first ever High Level Waste shipment from Sellafield.

More than ten years later than originally scheduled, the first shipment of vitrified High Level Waste (HLW) is expected to be shipped from Sellafield to Japan early in 2010. Sellafield Ltd announced November 25, that the first HLW return shipment to Japan was expected to be completed by next in March. Depending on which of three recognised sea routes was selected, the return could take up to 6 weeks – indicating a departure from the UK sometime in January 2010. It is likely that the HLW, loaded into transport containers, will be sent from Sellafield to Barrow docks by rail and loaded onto the Pacific Sandpiper for the 25,000km voyage to Japan.

The upcoming shipment will be the first repatriation of any category of foreign waste to overseas customers – despite Japanese and other wastes having been produced for more than thirty years by the reprocessing of Japanese spent fuel at Sellafield’s Magnox and THORP plant. Whilst  overseas reprocessing contracts signed after 1976 required customers to take back all reprocessing wastes, a system of ‘waste substitution’ was agreed between Government, Sellafield and customers in 2004 whereby only HLW would be returned – leaving the significantly larger volumes of Intermediate and Low level wastes to be disposed of in the UK. To compensate for the amount of radioactivity in those wastes that will remain in the UK, a ‘radiological equivalance’ will be returned to overseas customers in the form of additional HLW. For Japan, whose utilities will receive around 850 canisters of HLW directly resulting from their reprocessing contracts, the equivalence amounts to an extra 150 canisters, making 1000 in total.

Sellafield owners NDA have said that an overall total of 1850 HLW canisters are due to be repatriated to Japanese and European customers over the coming years. INS has confirmed that following the first return to Japan, the next HLW shipment will be to the Netherlands.

Source: CORE Briefing, 16 November 2009

Unlimited licence for Swiss nuclear power plant.

An environment ministry decision to grant an unlimited licence to the Mühleberg nuclear power station has prompted mixed reaction.The operators of the Mühleberg plant (outside the capital Bern) said they welcomed the move because it finally puts all five nuclear power stations in Switzerland on par with each other. The Mühleberg facility became operational in 1972 and had a licence that was due to run out by the end of 2012. An application has already been handed in to built a new reactor in ten years’ time.
Critics of nuclear power described the decision as irresponsible and scandalous. They pledged to challenge it in court. The Swiss Energy Foundation said the Mühleberg plant had safety problems. The technology used at the plant is also outdated according to the centre-left Social Democrats and the Green Party. In November 2009 voters in canton Vaud came out against extending the life of the plant beyond 2012. The governments in four other cantons which are customers of the plant were divided.
Source: Swissinfo.ch, 22 December 2009

Canada: Sept-Iles residents want Quebec to halt uranium mining.

Some 1,000 protesters gathered on December 13, in the town of Sept-Iles about 900 kilometers northwest of Montreal on the North Shore to protest against uranium mining. The residents continue to pressure Quebec to slap a moratorium on uranium exploration in the province, despite the government's promise to open a debate on health and safety concerns  surrounding the industry. The protesters were backing 20 doctors who threatened to quit their practice in the remote Quebec region because of plans to build a uranium mine nearby. "We're showing our support," said Marc Fafard, spokesman and founder of a grassroots group opposed to uranium mining in the province. "We want to show how proud we are of the doctors to have finally made this a provincial debate. Like it should be." The province's head of public health, Dr. Alain Poirier, met with the doctors the week before the demonstration and announced Quebec would create a special committee to study the potential risks of uranium exploration and mining on health and safety. The uranium debate has been raging in the region for more than a year, since mining company Terra Ventures Inc. began exploration for low-grade uranium near Lac Kachiwiss, some 20 kilometers north of Sept-Iles. Residents have concerns over the health and safety of uranium mines and fear the mining waste could contaminate local drinking water.

Source: The Canadian Press, 13 December 2009

Canada: Province threatens lawsuit over cost overruns. 

The Province of New Brunswick said Canada's federal government should cover cost overruns on the refurbishment of the Point Lepreau nuclear power plant or the province will sue Atomic Energy of Canada Ltd., according to the Canadian press reports. AECL is the government-controlled "crown corporation" that is performing the Can$ 1.4 billion (US$1.36 billion, 937 million Euro) renovation of Atlantic Canada's only nuclear power plant. The project was supposed to have been completed last September, but is running 18 months behind schedule. If the project remains behind schedule, officials say it could cost the province about $400 million (US$387 million) to buy replacement power. Under a memorandum of understanding signed last fall, New Brunswick won't be paid for Point Lepreau until the refurbishment is complete and the plant is generating electricity. This is the first refurbishment of a Candu-6 reactor and AECL is hoping to use Point Lepreau as a showcase to refurbish similar reactors around the world. In November two units of the Bruce A nuclear plant (earlier CANDU-types) have been given regulatory approval for refuelling and restart  after being out of service for more than a decade. Their major refurbishment (amongst others the replacement of fuel channels and steam generators) was over budget for almost Can$ 1 billion and 12 months behind schedule. (Read more in 'Restart go-ahead for refurbished Canadian units'; Nuclear Monitor 698, 27 November 2009)

Sources: Power Engineering International, 11 January 2010 / Nuclear Monitor 698, 27 November 2009

Heavy forging facility in India. 

Construction has started on a steel manufacturing and heavy forging facility in Gujarat state, India, as part of a joint venture between Nuclear Power Corporation of India Ltd (NPCIL) and Larsen & Toubro (L&T). During a ceremony on 9 January the foundation stone for the new facility was laid at L&T's existing manufacturing site in Hazira, Surat. The new facility will have a dedicated steel melt shop producing ingots of up to 600 tons, as well as a heavy forge shop equipped with a forging press that will be amongst the largest in the world. The facility will supply finished forgings for nuclear reactors, pressurizers and steam generators, and also heavy forgings for critical equipment in the hydrocarbon sector and for thermal power plants. L&T is India's biggest engineering and construction company and makes reactor pressure vessels for the country's pressurized heavy water reactors (PHWRs), fast breeder reactor and steam generators. It has been involved in supply of equipment, systems and services for nearly all the PHWRs that have been indigenously built, including the manufacture of calandrias, end-shields, steam generators, primary heat transport system and heat exchangers.

The capacity worldwide for heavy forging for nuclear reactors is very limited. At least in the short term, only one facility in the world, Japan Steel Works, can cast large forgings for certain reactor pressure vessels. JSW is aiming to produce sufficient forgings to supply theequivalent of about 8.5 sets a year by 2010 and the maximum ingot size is to be increased to 650 t.. The problem is the term “equivalent” because it is unclear how much of the forging capacity is dedicated in practice to new nuclear projects. JSW also supplies, for example, about 100 forgings a year for fossil fuel turbine and generator rotors to China alone.

Sources: World Nuclear news, 11 January 2010 / World Nuclear Industry Status Report 2009, M. Schneider, S. Thomas, A. Froggatt, D. Koplow