You are here

Argentina

Argentina, Armenia, Belgium

Nuclear Monitor Issue: 
#746, 747, 748
Waste special
01/05/2012
Article

Argentina

Nr. of reactors

first grid connection

% of total electricity 

2

1974-03-19

4.97 

The April 1997 National Law of Nuclear Activity assigns responsibility to the National Atomic Energy Commission CNEA (Comisión Nacional de Energía Atómica, founded in 1950) for radioactive waste management, and created a special fund for this purpose. Operating nuclear power plants pay into this. Awaiting final disposal interim storage of spent fuel takes place at cooling ponds on site, and some interim dry storage at Embalse.(*01) No reprocessing has taken place.

Final disposal
Final disposal of low-level waste takes place in engineering enhanced surface semi containment systems at the Ezeiza Radioactive Waste Management Area (AGE), operated by CNEA. For intermediate level wastes a monolithic near surface repository is foreseen, similar to those in operation in L’Aube, France and El Cabril, in Spain. (*02) Especially after a scandal in 2005 on high levels of water contamination with uranium in Ezeiza and Monte Grande, near the atomic center, doubts have risen about the conditions of and safety procedures at the AGE. The response from the CNEA and the government to the obvious contamination did not help to calm citizens’ worries, as it was marked by obscuring and silencing the real impact. A few years later the provincial government was forced to acknowledge the contamination values measured by independent laboratories, although official reports stated, that there was no contamination from nuclear waste but just high radioactive background level.(*03)

In 1994, during the nation's constitutional reform, a broad Argentinean environmental movement won a momentous victory to make Article 41, which bans the import of toxic and radioactive waste, part of the national constitution.(*04)

The Argentine Strategic Plan has provided three types of technological systems for final disposal:

  • Engineered Surface System, for LLW requiring isolation periods of up to 50 years.
  • Monolithic Near-Surface Repository, for ILW  requiring isolation periods of up to 300 years.
  • Deep Geological Repository, for HLW and SF requiring isolation periods in excess of 300 years.

With regard to spent fuel originating from research or radioisotope production reactors, the strategy considers two alternatives: Shipping them back to the country where they were originally enriched, if possible, or conditioning for final disposal.(*05)

The Strategic Plan, updated in March 2006, at present covers the period from 2006 through 2095.

The deadline to adopt a decision on the possible reprocessing or final disposal of spent fuel is subject to the completion of the studies for the siting of the Deep Geological Repository which have to be concluded at the latest by 2030. At such time the installation of the underground geological laboratory must have been started, which allows the design and construction of a deep geological repository, which must be operative by the year 2060. (*06)

Armenia

Nr. of reactors

first grid connection

% of total electricity 

1

1976-12-22

33.17%

The Government of Republic of Armenia established state regulatory authority for nuclear and radiation safety (ANRA). ANRA’s task is the state regulation of nuclear energy, including the safe management of radioactive waste. ANRA regulates the nuclear and radiation safety of Armenian NPP, dry spent nuclear fuel storage facility, ionizing radiation sources, RADON radioactive wastes storage facility, and of other facilities where practices with nuclear materials are implemented.(*01)

Spent fuel is stored in spent fuel pools. After five years of storage the spent fuel is placed into dry spent fuel storage (DSFS) and are placed into horizontal concrete storage modules (HSM). After Unit-1 shutdown its spent fuel pool is used as a temporary storage facility for spent fuel. (*02) DSFS started operation on 1 August 2000. The license validity is 20 years. DSFS consists of 11 horizontally placed concrete modules for storage of 616 spent fuel assemblies. In 2005 the National Assembly based on proposal from the government made decision to extend the DSFS. It will enable storing 1890 fuel assemblies at least 50 years.(*03)

Belgium

Nr. of reactors

first grid connection

% of total electricity 

7

1962-10-10

53.96%

In Belgium, after many years of discussion, a storage location has been selected for low-level and medium-level radioactive waste. It will take until 2070/80 before disposal of high-level radioactive waste will begin in clay layers.

Storage in sea
In Belgium, NIRAS (National Agency for Radioactive Waste and Enriched Fissile Materials) has been responsible for the storage of all nuclear waste. NIRAS, established in 1980, is supervised by the Ministry of Economic Affairs. From 1960 to 1982 Belgium dumped low-level radioactive waste in the Atlantic Ocean(*01) –described by NIRAS as "sea disposal at great depths".[*02] Since then NIRAS is studying the disposal of all types of nuclear waste aboveground or underground.

Low- and medium-level radioactive waste
In April 1994, NIRAS published a report on the aboveground storage of low-level radioactive waste. In all 98 mentioned suitable locations (in 47 municipalities), the report led to motions in town councils, in which storage was rejected.(*03).The government ask NIRAS if it would be possible to store the waste on one of the 25 military bases no longer in use. In June 1997, NIRAS published a report which "ultimately had only been a preparatory exercise, based on bibliographic data,"(*04) but nevertheless gave rise to concern again. Only the town council of Beauraing, where the military base Baronville is situated, was in favour of storage, but on 28 June 1998, in a local referendum 94 percent voted against.(*05) This brought embarrassment to the government, and as it often goes in politics, the government came with a woolly policy to work towards "a final solution or a solution with definite, progressive, flexible and reversible destination."(*06) According to this decision the low- and medium-level radioactive waste can be stored either close to the surface as well as in deep geological clay formations.(*07) The government no longer points to any sites, but puts the emphasis on public support and it assumes public support can be found at existing nuclear zones. These are Doel and Tihange (nuclear power stations), Mol (Center for Nuclear Energy Research), Dessel (manufacture of fuel elements) and Fleurus (Institute for radio-elements). But towns may present themselves also voluntarily.(*08) NIRAS adopted the government's policies and stated in 1998: "To strive for a real partnership from the beginning, rather than merely an exchange of arguments, means a modernization for the nuclear waste sector."(*09)

In 1999, after much deliberation, NIRAS signed a partnership agreement with Dessel and Mol, and on June 23, 2006 the choice fell on Dessel. In 2004, the population of Dessel had already voted in favour of the so-called surface disposal, which is planned to start in 2016.(*10) The waste (appr. 70,000m3) will be stored in what ultimately will be a hill of 160 by 950 meters and 20 meters high. Barrels put in boxes filled-up with concrete (monoliths), will be placed in modules and covered with mutiple layers. Taking into account the additional buildings, the storage requires 74 acres (30 ha). After 50 years, the storage is completed, and then it can be decided whether the roof is replaced by a definitive cover. It should be possible to retrieve the monoliths in the first 200-300 years when there will be active monitoring of the waste.(*11)

High-level radioactive waste
Since the early 1970s, Belgium has plans to store high-level radioactive waste in clay layers. From 1974 to 1989 research and construction of an underground mine (at a depth of 230 meters) into the clay under Mol in the Kempen region took place. This is a particular type of clay, the so-called “Boomse klei” (Boom clay), which is also present in some parts of the Netherlands. According to NIRAS, Belgium opted for clay because there was data available. The choice fell on Mol ("Apart from its intrinsic qualities, the Boom clay has the advantage of being located under the nuclear site at Mol-Dessel.") because this town is hosting the national Center for Nuclear Energy Research with the (closed) Eurochemie reprocessing plant: "to have available a local solution for eventual disposal of reprocessing waste from the Eurochemic plant".(*12)

Between 1990 and 2000 methods to assess the safety and the properties of clay for the long term were studied. One of the important questions what would happen if nuclear waste is leaking from the barrels and ends up in the clay? The NIRAS 2002 SAFIR (Safety Assessment and Feasibility Interim Report) 2 report states that many questions about the safety of storing nuclear waste in clay remain unanswered: until 2017, therefore eleven issues have to be examined with priority.

Until 2017, NIRAS will show the feasibility of the studied solution and demonstrate how the nuclear waste has to be disposed of. Then construction of the storage mine may start. In the complicated words of NIRAS: "Without frustrating the basic choice of the Boom clay, at this moment there still remain important questions unanswered, therefore it is premature to make a definitive statement today on the technical feasibility of storage in this formation or on the operational and long-term safety of such disposal."(*13)

Keeping in mind there is still no decision on disposal of high-level radioactive waste in clay yet),  the NIRAS' Board of Directors adopted a 'Waste Plan' on 23 September 2011.(*14) "Now the legal procedure for the Waste Plan is completed and the dossier is ready to be delivered to the government which then will have all the ingredients to make a decision. With a basic decision of the government clarity will be obtained which direction further work has to be done on how long-term safety can be guaranteed. The basic decision will be the first step in a gradual, lengthy decision-making process in which the society will be involved. The process leading to the implementation of a long-term management option will take several decades. Currently, it is not about selection of a location. That choice, at which the local population will be 'closely involved', will be made at a later stage in the decision-making process.”(*15) If the government opts for storage in clay, it will take until 2070-2080 before the disposal of high-level radioactive waste can begin.(*16)

References:

Argentina:
*01- World Nuclear Association: Nuclear Power in Argentina, November 2011
*02- Republica Argentina: Third National report Joint Convention on the Safety of Spent Fuel Management and on the Safety of Radioactive Waste Management, 2008, section B-7
*03- Michael Alvarez Kalverkamp: Argentina: Uncertainty about the nuclear future, Heinrich Boell Foundation, 18 April 2011
*04- Greenpeace: Argentina next nuclear dump for the world?, 8 November 2002
*05- IAEA: Country profile: Argentina
*06- Republica Argentina, Section B-1

Armenia
*01- ANRA: ANRA Regulatory Activity, Installations subject to Regulation and Legal Bases, website, April 2012.
*02- ANRA: Convention on Nuclear Safety, Fifth national report of the Republic of Armenia, September 2010.
*03- ANRA: Dry Spent Fuel Storage Facility, website, April 2012

Belgium
*01- IAEA: Inventory of radioactive waste disposals at sea, IAEA-Tecdoc-1105, August 1999
*02- NIRAS: Het beheer van het radioaktieve afval, vouwblad 7: De berging van het radioaktieve afval, (The management of radioactive waste. Folder 7; the disposal of radioactive waste), Brussels, no date.
*03- Erik van Hove: Accounting for Socio-economic Effects in Nuclear Waste Disposal Projects, in: Nuclear Energy Agency, "Informing the Public about Radioactive Waste Management", Proceedings of an NEA International Seminar, Rauma, Finland, 13-15 June 1995, Paris, 1996, p 161-171
*04- NIRAS: press release, Brussels, 16 March 1998, p 3
*05- TV België-1: journaal (national TV-channel news) 19.00 hr, 28 June 1998
*06- NIRAS: Informatiefiche, Brussels, 2 March 1998
*07- Nuclear Energy Agency: Radioactive Waste Management Programmes in OECD/NEA Member Countries, Belgium, Paris, 25 May 1998
*08- NIRAS: Informatiefiche, Brussels, 2 March 1998, p. 11
*09- NIRAS: Partnerschap staat centraal in nieuw werkprogramma van NIRAS, (Partnership is central issue in new working program of NIRAS), press release, Brussels, 16 March 1998, p. 3-4
*10- NIRAS: Het langetermijnbeheer van categorie-A afval  (2006) (The long-term management of Category-A waste)
*11- NIRAS: Final report De berging, op Belgisch grondgebied, van laag- en middelactief afval met korte levensduur, 2006 (The storage, on Belgian soil, of short lived low and intermediate level waste)
*12- NIRAS: SAFIR Syntheseverslag (SAFIR Synthesisreport), Brussels, June 1989, pp. 7 and 8
*13- NIRAS: Naar een duurzaam beheer van radioactief afval (Towards a durable management of nuclear waste), SAFIR 2 and it's context, report NIROND-2001-07N, 4 February 2002.
*14- NIRAS: Press release Afvalplan (Wasteplan) Brussels, 23 September 2011
*15- ONDRAF/NIRAS, Executive summary Afvalplan voor het langetermijnbeheer van geconditioneerd hoogradioactief en/of langlevend afval en overzicht van verwante vragen, September 2011. (Waste plan for long term management of conditioned high-level waste and/or long-living waste and overview of relevant questions) report NIROND 2011-04.
*16- Sigrid Eeckhout (NIRAS), email to Herman Damveld on 8 December 2009, 15.51 hr.

In brief

Nuclear Monitor Issue: 
#734
07/10/2011
Shorts

Oppose Nigeria's nuclear plans.
On September 15, President Goodluck Jonathan formally inaugurated Nigeria's Atomic Energy Commission and urged its members headed by Erepamo Osaisai to quickly evolve implementable plans and timelines for the delivery of atomic energy for peaceful purposes in the country. We recall that the Nigeria Atomic Energy Commission was established in 1976 to investigate the development of nuclear energy but little progress was made. It was reactivated in 2006 and President Jonathan appointed a new team this year.

Nigeria has the world's seventh-largest natural gas reserves, yet the nation is blighted by persistent electricity outages which force businesses and individuals who can afford them to rely on generators. Much of this vast gas reserves sit untouched under the ground or are flared into the sky. Despite being Africa's biggest crude oil exporter, decades of corruption and mismanagement mean Nigeria has never built the infrastructure to farm its huge oil and gas resources for much-needed domestic use.

Deficits in our existing institutions remain a defining albatross on the path to meaningful development. Cut to the bone, this scenario suggests that Nigeria currently lacks the indigenous capacity, supporting infrastructure, discipline and security wherewithal to build and manage an atomic power plant. It simply is another way of courting disaster - one we cannot manage.

Let us explore and exploit other safer, rational options. These include solar, gas, hydro, wind and coal options. Nigeria has these resources in stupendous quantities. A presidential directive requesting timelines for the generation of electricity through these options is far better than the timelines he recently demanded from the newly-inaugurated Atomic Energy Commission. Our scientist-president should think again.
Editorial Leadership newspaper (Nigeria), AllAfrica.com, 3 October, 2011


Belene construction agreement extended.
Russia's AtomStroyExport (ASE) and Bulgaria's National Electricity Company (NEK) have signed a supplement to their agreement on the construction of the Belene nuclear power plant, extending it until the end of March 2012. Under an earlier extension, the agreement - originally signed in 2006 - was extended until 30 September. According to ASE, the extension 'confirms the parties' interest in the continuation of the project.' NEK said that during the next six months, the two companies will continue their activities related to completing a market study, clarifying the financial model and studying the project finance proposal submitted by financial advisor HSBC. It added that the extra time will allow Bulgaria to conduct an analysis of the results and recommendations of stress tests being performed at nuclear power plants across the European Union. ASE said that work on the foundation pit for the first reactor at Belene has now been completed. It said that a concrete plant at the site has already been put into operation and that water treatment plants have been built.
World Nuclear News, 03 October 2011


UAE: Construction first unit will start mid-2012.
According to the Emirates Nuclear Energy Corporation (Enec), a government establishment created last year to oversee the ambitious nuclear construction project, said it would launch construction work for the infrastructure of four planned nuclear power plants in Barrakah in the western region in mid 2012 to pave the way for their operation in 2017. The UAE will award a contract in early 2012 for the supply of nuclear fuel to run its four nuclear reactors which the country is planning to construct as part of an ambitious nuclear power program.

Under the agreement to built 4 nuclear reactors, inked on December 27, the state-owned Korea Electric Power Corp (Kepco) and is partners in the consortium will design, build and run the reactors that will produce 5,600 MW of electricity. The contract to build the reactors is worth about US$20 billion (15bn euro).

The UAE has said the project is intended to diversify its energy supply sources and meet its rapid growing electricity demand, which is projected to surge to around 40,000 MW in 2020 from nearly 15,000 MW in 2009. The nuclear project will provide nearly 25 per cent of the UAE’s total energy needs of nearly 40,000 MW in 2020. Around seven per cent will be generated through renewable energy and the rest through conventional means.
Emirates 24/7, 25 September 2011


Pyhäjoki location for Finland's sixth reactor.
Fennovoima has chosen Pyhäjoki as the site for its nuclear power plant. Pyhäjoki municipality is located in North Ostrobothnia and the nuclear power plant will be constructed on Hanhikivi peninsula on the coast of Bothnian Bay. For the basis of the site selection, assessments were carried out during some four years. In the beginning of Fennovoima project in summer 2007, the company had almost 40 alternative sites. The number of alternatives was decreased gradually based on assessments and in December 2009 Fennovoima ended up having two alternatives, both located in Northern Finland: Pyhäjoki and Simo municipalities. In the final site decision, safety, technical feasibility, environmental matters, construction costs and schedule were the main factors examined as well as the ability of the site region to support a project that will bring thousands of people to work and use services there.

Fennovoima continues now the planning work together with the municipality, authorities and the plant suppliers and prepares applying for various licences and permits. For example, more detailed bedrock, environmental and water studies will be carried out on the Hanhikivi peninsula. Simultaneously, other preparations for the future phases of the project are carried out together with Pyhäjoki and Raahe region. First preparatory works on Hanhikivi will be started in the end of 2012 at earliest. The construction schedule will be elaborated after the plant supplier has been selected. Fennovoima sent bid invitations for Areva and Toshiba in July 2011 and the plant supplier will be chosen in 2012-2013.

Fennovoima has two owners: Voimaosakeyhtiö SF and E.ON Kärnkraft Finland. Voimaosakeyhtiö SF owns 66 percent of Fennovoima and nuclear expert E.ON Kärnkraft Finland 34 percent. Altogether Fennovoima has 70 shareholders. Voimaosakeyhtiö SF is owned by 69 finnish regional and local energy companies as well as companies in trade and industry.

Finland has 4 reactors in operation (two at Lovisa and two at Olkiluoto). The fifth (Olkiluoto-3) in under construction; over budget and over time.
Press release Fennovoima, 5 October 2011 / IAEA Reactor database.


Health effects radiation suppressed by tobacco companies.
Tobacco companies knew that cigarette smoke contained radioactive alpha particles for more than four decades and developed "deep and intimate" knowledge of these particles' cancer-causing potential; however, they deliberately kept their findings from the public. The study, published online in Nicotine & Tobacco Research, the peer-reviewed journal of the Society for Research on Nicotine and Tobacco, adds to a growing body of research detailing the industry's knowledge of cigarette smoke radioactivity and its efforts to suppress that information. The UCLA researchers analysed  dozens of previously unexamined internal tobacco industry documents, made available in 1998 as the result of a legal settlement.

“The documents show that the industry was well aware of the presence of a radioactive substance in tobacco as early as 1959; furthermore, the industry was not only cognizant of the potential 'cancerous growth' in the lungs of regular smokers but also did quantitative radiobiological calculations to estimate the long-term lung radiation absorption dose of ionizing alpha particles emitted from cigarette smoke." The study’s first author, Hrayr S. Karagueuzian, a professor of cardiology who conducts research at UCLA's Cardiovascular Research Laboratory, said: ‘We show here that the industry used misleading statements to obfuscate the hazard of ionizing alpha particles to the lungs of smokers and, more importantly, banned any and all publication on tobacco smoke radioactivity.” 

The radioactive substance, which the UCLA study shows was first brought to the attention of the tobacco industry in 1959, was identified in 1964 as the isotope polonium-210, which emits carcinogenic alpha radiation. Polonium-210 can be found in all commercially available domestic and foreign cigarette brands, Karagueuzian said, and is absorbed by tobacco leaves through naturally occurring radon gas in the atmosphere and through high-phosphate chemical fertilizers used by tobacco growers. The substance is eventually inhaled by smokers into the lungs.
LA Examiner, 28 September 2011


Dounreay: Belgium waste to be returned.
Dounreay has announced the return of reprocessing wastes from the BR2 research reactor in Belgium. The BR2 reactor in Mol was a good customer for Dounreay over the years, receiving new enriched uranium fuel from the reprocessed spent fuel. It planned to send considerably more spent fuel to Dounreay but the reprocessing plant was closed by a leak and never reopened. Wastes have already been returned to France and Spain. One Dounreay reprocessing customer has requested the substitution of vitrified high-level wastes for the intermediate level wastes at Dounreay (a consultation on this was held in 2010). However, Belgium wants to take back the intermediate level waste, as required by the original contract with Dounreay. Dounreay also had contracts with Australia, Germany and for Italian-owned fuel from Denmark.

There are 153 tons of BR2 reprocessing wastes cemented into 500-liter drums and this will involve an estimated 21 shipments over four years, starting this autumn. The shipments will be from Scrabster and will probably involve the former roll-on/roll-off ferry, the Atlantic Osprey.
N-Base Briefing 689, October 2011


IAEA Inspector exposed to radiation.
On October 5, the International Atomic Energy Agency (IAEA) reported that one of its nuclear inspectors had been exposed to radiation during a 4 October inspection of the Belgoprocess nuclear waste facility in Dessel, Belgium. The inspector, along with an inspector from Euratom and a Belgoprocess employee, apparently received a dose of radiation after a vial or flask of plutonium accidentally fell on the floor, according to releases from the company and the Belgian Federal Nuclear Control Agency (AFCN). Plutonium is dangerous if ingested, but the amount received by the inspectors was less than the legal limit, the AFCN says. No radiation has been released beyond the site.
Nature.com, 5 October 2011


Atucha II, Argentina's third nuclear power plant.
President Cristina Kirchner inaugurated Atucha II, Argentina's third nuclear power plant on September 28. The German-designed reactor is expected to be fully operational in six to eight months after engineers run a series of tests. Construction of the plant began in July 1981, but work soon stopped and did not resume until 2006, when then-president Nestor Kirchner (2003-2007), the current leader's late husband, ordered the plant to be completed.

Argentina's other nuclear plants are Atucha I (335 megawatts) and the Embalse plant (600 megawatts). Once Atucha II is online 10 percent of Argentina's electricity will be produced by nuclear power. Plans are on the drawing board for Atucha III plant as well as an overhaul of the Embalse plant to add 30 years to its operational life, said Planning Minister Julio de Vido. Embalse was connected to the grid in 1983. Atucha II is located on the banks of the Parana river in the town of Zarate, some 100 kilometers north of the capital Buenos Aires. It was built at a cost of more than 2.4 billion dollars.
AFP, 29 September 2011


Another USEC deadline for DOE loan guarantee.
On September 30, USEC, announced morning it will reduce its spending on the American Centrifuge Project (ACP) in Piketon by 30 percent over the next month. It will also send out notices to its 450 employees Ohio, Tennessee and Maryland that layoffs are possible if the company doesn’t receive a loan guarantee before October 31. USEC has invested approximately US$2 billion in the ACP but needs significant additional financing to complete the plant. In 2008, USEC applied for a US$2 billion loan guarantee from Department of Energy for construction of the ACP. USEC significantly demobilized construction and machine manufacturing activities in 2009 due to delays in obtaining financing through DOE’s Loan Guarantee Program. Since then, many 'final' deadlines were set by USEC (three in the past half year: June 30, Sept. 30 and now Oct, 31) to obtain the loan guarantee.

In a call with investors, USEC President and CEO John Welch said the company must see a loan guarantee during the next month or risk the end of the project. USEC expects October “to be a month of intense interaction with the DOE,” in hopes of securing the loan guarantee.

The company had faced a September 30 deadline with two investors — Toshiba America Nuclear Energy Corporation and Babcock & Wilcox Investment Company — to receive a US$2 billion loan guarantee. They agreed September 30 to extend that deadline to October 31. If USEC receives the loan guarantee, the companies have promised US$50 million to support the project.

In a statement, DOE Spokesman Damien LaVera said, “The Department of Energy has been working closely with USEC as the company has continued to test and validate its innovative technology, obtain private financing and meet other benchmarks that would be required for a successful loan guarantee application. We are strongly committed to developing effective, domestic nuclear enrichment capabilities and are looking at all options on a path forward.”

The ACP will utilize USEC’s AC100 centrifuge machine, which has been developed, engineered and assembled in the US. The AC100 design is a disciplined evolution of classified U.S. centrifuge technology originally developed by DOE. DOE invested already US$3 billion over 10 years to develop the centrifuge technology.
Dayton Daily News, 1 October 2011 /  ACP website: www.americancentrifuge.com


Taiwan: nuclear accident compensation increased.
On September 30, the Taiwanese Cabinet approved an amendment to the Nuclear Damage Compensation Act that imposes heavier compensation liability on nuclear power operators in the event of natural disasters such as an earthquake or a typhoon. Under the amendment, the maximum amount of compensation for losses caused by a nuclear accident was increased from NT$4.2 billion (US$138 million or 103 million euro) to NT$15 billion (US$5 mln or 3.7 mln euro) and the allowed period for compensation claims was extended from 10 to 30 years.

The amendment came after the Atomic Energy Council reviewed the act, which had not been amended since it was first enacted in 1997, in the wake of the nuclear accident at Japan’s Fukushima Daiichi Nuclear Power Plant. Democratic Progressive Party Legislator Tien Chiu-chin said the amendment fell short of her expectations as she had suggested further lifting the ceiling on compensation liability.
Tapei Times, 30 September 2011


36 year old construction permit extended. The US Nuclear Regulatory Commission (NRC) has extended the construction permit for the unfinished Bellefonte unit 1 in Alabama.
The construction permit was originally granted in 1974. It was suspended in 1988, when Tennessee Valley Authority (TVA) decided to halt work on the project, but the NRC agreed in 2009 to reinstate the permit. With the reinstated permit due to expire on 1 October 2011, TVA lodged an application for an extension in October 2010. The NRC has now agreed to that extension, meaning that the construction permit will remain valid until 1 October 2020. (see more in Nuclear Monitor 732, 9 September 2011)
World Nuclear News, 03 October 2011


Swiss parliament, no new reactors.
On September 28, the Council of States has followed the government’s lead by voting not to replace the country’s five nuclear power stations  and boost renewable energy resources. Switzerland currently has five nuclear power plants that will gradually come off the power grid at the end of their 50 year (!) lifespan: the first one in 2019 and the last one in 2034. The Senate followed the House of Representatives in calling on the government to ban new nuclear plants but keep parliament "informed about innovations in the field."

The clear result of the September 28 vote - with a three to one majority - came after a parliamentary committee prepared a compromise formula, promoted by the centre-right Christian Democratic Party, which will give parliament another chance to have a say at a later stage. “Even if we were to ban nuclear power plants now our successors in parliament could still one day decide on building on new reactors,” a Christian Democratic Senator, Filippo Lombardi from Ticino, said on behalf of the committee. Discussions on nuclear power are due to continue in the new parliament which is due to convene for the first time in December following general elections next month.

The Social Democrats, the Greens as well as the Christian Democratic Party hailed the Senate decision as an important step towards a new energy policy amid calls for further measures to switch to more renewable energy sources.

The government called for a withdrawal from nuclear energy in May – a proposal backed by the House of Representatives a month later.
Swissinfo.ch 28 September 2011


Hinkley Blockaded: No New Nuclear Power!
More than 300 people (even up to 400, according to a BBC-report), successfully sealed off the main entrance to Hinkley Point nuclear power station in Somerset for nine hours on 3 October in opposition to EDF Energy's plans to build two new mega-reactors on the site. EDF said of 500 employees at the plant, only essential staff had been called in and had arrived by bus at dawn.

Blockaders were joined by a theatrical troupe who enacted a nuclear disaster scenario, while Seize the Day provided a musical backdrop to the event. 206 helium balloons were released to represent the number of days since the Fukushima meltdown. The balloons will be tracked, to show which areas of the West Country would be worst affected by a nuclear disaster at Hinkley.
Indymedia.uk; www.stopnewnuclear.org.uk; BBC, 3 October 2011

In brief

Nuclear Monitor Issue: 
#718
29/10/2010
Shorts

Argentina reactivates enrichment plant.
Argentina has formally reactivated its gaseous diffusion uranium enrichment plant at Pilcaniyeu over two decades after production there halted. The plant is expected to become operational in September 2011. Plans to recommission the Pilcanyeu plant, which operated from 1983 to 1989, were announced in 2006 and form part of Argentina's ambition to build a self-sufficient nuclear fuel cycle. Work has been underway to refurbish and upgrade the plant, which uses gaseous diffusion, using Argentina's own technology. The first stage of the refurbishment has involved the construction of an advanced prototype of 20 diffusers, and the plant is expected to be able to produce its first enriched uranium for nuclear fuel use by September 2011 according to the CNEA. President Fernandez said that in reactivating the plant, Argentina was recovering lost time. She described uranium enrichment as "a right that we should never have resigned." The project was "a source of great pride" for the country, she said. The original Pilcaniyeu plant had a modest enrichment capacity of 20,000 SWU per year, although plans call for the upgraded plant ultimately to reach a capacity of some 3 million SWU.
Source: World Nuclear News, 26 October 2010


INES 20 years old.
Jointly developed by the IAEA and the Nuclear Energy Agency (of the OECD) in 1990, in the aftermath of the Chernobyl accident, the International Nuclear and radiological Event Scale (INES) helps nuclear and radiation safety authorities and the nuclear industry worldwide to rate nuclear and radiological events and to communicate their safety significance to the general public, the media and the technical community. INES was initially used to classify events at nuclear power plants only, but since 2008, INES has been extended to any event associated with the transport, storage and use of radioactive material and radiation sources, from those occurring at nuclear facilities to those associated with industrial use. INES has mainly become a crucial nuclear communications tool. Over the years, national nuclear safety authorities have made growing use of INES, while the public and the media have become "more familiar with the scale and its significance". According to the OECD Nuclear Energy Agency "this is where the true success of INES stands, having helped to foster transparency and to provide a better understanding of nuclear-related events and activities".
Source: Nuclear Engineering International, 22 October 2010


International Uranium Film Festival 2011 in Brazil.
For the first time in history Brazilians will be able to see international independent Nuclear-Energy and Uranium-Documentaries in cinema. The film and video festival Uranio em Movi(e)mento - 1st International Uranium Film Festival 2011 will help to bring the Uranium- and Nuclear question into the national and international public. The deadline  for entries is January 20, 2011. The Uranium Film Festival wants to inform especially the Brazilian and Latin American societies and stimulate the production of independent documentaries and movies about the whole nuclear fuel cycle, about the dangers of radioactivity and especially about the environmental and health risks of uranium exploration, mining and processing. The Uranium Film Festival will be held from May 21 to 28, 2011 in the city of Rio de Janeiro and from June 2 to 9 in the city of Sao Paulo.

Until today most of the documentaries about uranium and the nuclear risks are mainly in English, German or French - but not in Portuguese. So the second advantage of our Uranium Film Festival is to subtitle the films to create the so called Yellow Archives. Yellow is the color of Uranium and for that a symbol for the whole nuclear industry.

The Yellow Archives will be the first-ever film library in Brazil and Latin America dedicated to films about the whole nuclear fuel chain organized by the Uranio em Movi(e)mento Festival. Believing that awareness is the first step in making positive changes to better our environment, the Yellow Archives hopes to increase public awareness especially in Brazil and in other Portuguese speaking countries like Portugal or Angola and Mozambique. The DVDs will be used for non-profit, educational and research purposes. Especially schools, universities, environmental groups and other grass root movements will have access to the Yellow Archives.
Contact  and source:  info@uraniumfestival.org / Website: www.uraniumfestival.org


India: antinuclear activists arrested.
On October 6, eleven activists of "Paramanu Bidyut Birodhi Prachar Andolan" (Campaign against Nuclear Power) were forcefully seized by the local police while distributing leaflets opposing the proposed Haripur nuclear power plant, in the vicinity of Saha Institute of Nuclear Physics in Kolkata, where Dr. Srikumar Banerjee, the Atomic Energy Commission Chairman, had arrived to preach the merits of setting up of a 'nuclear park' at Haripur. The handful of activists present had not even entered the institute campus and were distributing leaflets on the road outside. First one activist was forced into a police jeep and hauled away to the local police station. The rest were pushed away from the immediate vicinity of the Saha Institute. But when the activists continued distributing their leaflets, a police van was brought in, the police suddenly pounced, herded the activists into a police-van and taken to the local station. The activists were held for over 6 hours in the name of interrogation. However, no actual interrogation was conducted. For the real reason for detention, which the officers divulged off-the-record, was to keep the activists away from the site (where the vast benefits of nuclearisation was being preached). That, in their minds, was the ideal way of handling critics and criticism.
Source: Radicalsocialist.in, 7 October 2010


Vermont Yankee tritium leaks into aquifer.
The leaking radioactive tritium from Vermont Yankee has now leaked into the aquifer that drinking water is pulled from in and around the town of Vernon, Vermont. Entergy Louisiana, the corporate owners of Vermont Yankee, could do more to contain the contamination but are refusing. The Vermont Department of Health and the Agency of Natural Resources are doing nothing to require Entergy to increase the cleanup effort. More is needed to pressure the state agencies into action. When the Oyster Creek Nuclear Reactor in New Jersey contaminated the ground water with radioactive tritium the NJ Department of Environmental Protection took enforcement action. When the Braidwood Station Nuclear reactor in Illinois contaminated the ground water and then the drinking water aquifer of the local community the Illinois EPA took enforcement action. Entergy Vermont Yankee, likely leaked radioactive materials into our state's ground water for two or three years and now it is clear that at least some of that contamination has also gotten into the local drinking water aquifer. Continued pumping, at deeper depths, should be able to keep hundreds of thousands if not millions of gallons of contaminated water from migrating further into the aquifer and yet there has been no talk from your agencies about requiring even this simple step.  Instead Entergy Vermont Yankee is planning on ending all of their pumping in December. Ultimately, the contaminated soil needs to be removed and that can't happen until the plant is retired and cleaned up.

Vermont Yankee is scheduled to close in March of 2012. It is one of the oldest reactors in the country but its owners, Entergy Corporation, want to run it for 20 years past its expiration date. Poor management and old age have lead to a string of accidents and safety concerns.
Entergy has refused to add money to the reactor's clean-up fund, potentially leaving Vermonters with most of a $1 billion dollar clean-up bill in addition to the nuclear waste that is being stored on the banks of the Connecticut River.
On February 23, 2010, and by a margin of 26 to 4 the Senate voted to retire the Vermont Yankee nuclear plant as scheduled. This historic vote marks the first time a state legislature has been able to deny a nuclear plant a 20-year life extension. In March, fifteen towns voted on town meeting to close Vermont Yankee as scheduled. That combined with the 36 towns that voted in 2009, a total of 51 towns, have spoken -- they want Vermont Yankee to close as scheduled.

The public sentiment expressed by the town meeting votes this year and last show overwhelming opposition to continued operation of Vermont Yankee after 2012 and very strong support for requiring Entergy to fully fund the cleanup and for safe, clean and renewable sources of electricity.

The resolution calls for the plant's closure in 2012 and for Entergy-- the owner of Vermont Yankee-- pay for the full cost of decommissioning the plant. A vast majority of Vermonters know Entergy cannot be trusted.
Source: www.vpirg.org


U.S.A.: Hanford cleanup; new deadlines.
Washington state and federal officials have agreed on a new schedule for the cleanup of the Hanford nuclear reservation. The good news is that the federal government could no longer ignore cleanup deadlines with impunity. The bad news is that the agreement would push the deadlines forward by more than two decades. Under the new cleanup schedule, 53 millions gallons of radioactive waste stored in 177 underground tanks near the Columbia River would not have to be emptied until 2052. That's a 24-year delay from the existing timetable. (see more on the Hanford tanks, Nuclear Monitor 696, October 23, 2009). Thirty-five of those tanks are double-walled and considered 'reliably safe'.  All of the 142 single-walled tanks would have to be emptied by 2047 under this new schedule. And the tanks of most concern — the 67 single-walled tanks known to be leaking — would be emptied by 2014. It's estimated that more than 1 million gallons (1 US gallon is 3.787 liter) of radioactive waste already have leaked. Some of that waste has made it into the groundwater and is slowly moving toward the nearby Columbia River.

The state has long sought to make Hanford cleanup deadlines enforceable in court. Until now, the federal government has steadfastly refused to do so and now the government finally agreed to the court-enforceable deadlines. This accountability has become critical. Without it, there can be little confidence that the government would adhere to any cleanup schedule. The federal government has failed to meet numerous deadlines established in the 1989 Tri-Party Agreement signed by the Energy Department, the Environmental Protection Agency and the state of Washington. It's not as though the state has refused to be flexible. Washington has agreed to more than 400 changes in the Tri-Party Agreement. Yet as recently as last year, the government missed 23 project deadlines.
Source: The Daily News Online (tdn.com), 19 October 2010


South Africa: six reactors up and running in 2023.
On October 7, The department of Energy of South Africa published an ambitious plan to reduce SA reliance on coal by almost half by 2030 and to more than double the use of nuclear energy The proposals, which are part of the department's draft integrated electricity resource plan (IRP), show the government's preferred energy mix for the next 20 years. They provide prospective investors with an indication of the shape of South African future energy industry. The integrated resource plan is a 20-year electricity capacity plan that gives an outcome of projected future electricity demand, how the demand would be met and at what cost.

In the draft IRP, the department is proposing that coal contribute 48% to the energy mix by 2030, followed by renewable energy (16%), nuclear (14%), peaking open cycle gas turbine (9%), peaking pump storage (6%), mid-merit gas (5%) and baseload import hydro (2%).  Coal currently accounts for over 90% of electricity generation. Eskom's two nuclear reactors at the Koeberg power station supply 1800MW or 6% of SA's electricity needs. The renewable energy industry is yet to take off in SA. The draft plan envisages average gross domestic growth of 4,6% on over the next 20 years, which would require 52 248 MW of new power generation capacity to be brought on line. The government plans to build six new nuclear power stations which are expected to be up and running by 2023. Only  a few months ago, the government stopped the PBMR-nuclear project after it poured billions in it over the last decades.
Source: Eastcoast radio, 8 October 2010 / Engineering News (SA), 8 October 2010


CEZ delays Temelin reactors.
CEZ AS, the Czech Republic's largest power producer, will delay the construction of two  additional reactors at its Temelin nuclear power plant, Hospodarske Noviny reports, citing Industry and Trade Minister Martin Kocourek. The construction could be delayed by as much as several years, the newspaper said,citing an unidentified person from the company. The main reason is uncertain demand for electricity after 2020, according to the report. CEZ selected Westinghouse Electric Co., Areva SA and a Russian-Czech consortium led by ZAO Atomstroyexport as the three bidders for the contract.

This is good news for the whole CEE region. Until recently, CEZ has been agresivelly pushing construction of 5 new reactors in the region (2 in Czech Republic, 1 in Slovakia,  other 2 to be determined). But now the plans are put to ice, citing less demand and lower  prices on electricity markets, as well as less optimistic rating outlook of the utility. But there are more interesting details in original Hospodarske Noviny article: Quoting for example an internal CEZ document: "The expansion plans were based on increasing of our [CEZ] debt. But we are not anymore sweetheart of the markets, we are not considered as a stable and growing corporation, we are getting first signals from rating agencies..."

Similarly to EdF, CEZ already had to reduce its investment program by 2015 from 425 to 333 billion CZK [ca 13 billion EUR], and this is not enough - it admits the cuts will have to be deeper.
Source: Email: Greenpeace International, 13 October 2010


New press for reactor pressure vessels.
A major new facility has been commissioned in Germany for the production of large reactor components. The 12,000 ton press installed at Völklingen by Saarschmiede GmbH Freiformschmiede can handle ingots of up to 370 tons - enough to make all but the largest reactor pressure vessels. The time for construction was only two years. Due to its geometrical dimensions," the company said, the press is "able to deal with all parts of the AP1000." It estimated that some four to six sets of heavy forgings for AP1000s could be made annually at the facility, given certain other expansions. Westinghouse has sourced forgings from South Korea's Doosan Heavy Industries for the four AP1000s under construction in China as well as the four forthcoming units at Vogtle and Summer in the USA.
Source: World Nuclear News, 14 October 2010


Chernobyl 1986-2011
Next year April marks the 25th anniversary of the disaster in the Chernobyl nuclear power station, in the Ukraine. For sure there will be many commemorative activities taking place all over the globe. WISE will, starting next issue, try to cover relevant developments and news on Chernobyl in the Nuclear Monitor, and we would like to start listing as much as possible activities, publications, actions, official reports, meetings and conferences on this issue.

With several other NGO’s in different parts of the world we are preparing a joint call for action. You will hear from us soon, we hope to hear from you aswell; please send in anything you have heard about activities on the coming Chernobyl Day. In the meantime; join the Virtual March on Washinton, for April 26, as part of an International Radioactive Waste Action Day. Go to http://www.nirs.org/radwaste/actionday/dayhome.html

Argentina: court halts open-pit uranium mine

Nuclear Monitor Issue: 
#709
6046
12/05/2010
Article

An Argentine high court halted the project of a foreign company to mine uranium in an open-pit mine in Quebrada de Humahuaca in the northern part of the country, declared a World Heritage of Humanity site in 2003, according to local press reports. One year ago, on May 7, 2009, 2000 persons held a protest march from Juella to Tilcara against uranium exploration in the Quebrada de Humahuaca area. It was the second demonstration in a year in the aera, because on July 8, 2008, also two thousand residents of several localities demonstrated against the proposed uranium mine.

After losing their case against the mining exploration permits in the Quebrada de Humahuaca area before the administrative court, the NGO Los Vecinos Autoconvocados de Tilcara filed an appeal with the Superior Court of Justice in San Salvador de Jujuy on May 7, 2009. The decision of the Supreme Court of Jujuy province, handed down in February but made known to the interested parties in April, favored the suit for protection filed by inhabitants and environmentalists of the town of Tilcara, which is near Quebrada de Humahuaca.  It denied an April 2009 ruling by a court of appeals favorable to the interests of the mining company Uranios del Sur, and also obliges the company to show that its project would not contaminate the environment.

“The sentence changed the judicial paradigm in bringing environmental law into mining activities,” Alicia Chalabe, attorney for the inhabitants of Tilcara, told a Buenos Aires daily. She said that “there are many cases” that have been brought in the Argentine provinces “against the negative influence of mining, but the courts always refer to the Mining Code and give no hearing to environmental law.”
The Supreme Court of Jujuy, a province bordering on Bolivia, halted the mining project “until it is shown that there is no possibility or certain danger that the work carried out in the area will cause contamination or environmental damage,” according to the court ruling published in the Buenos Aires newspaper.

The court said that “it is the duty of judges” to immediately “make effective the judicial protection of the reserve and of the collective interests” of the villages near the Quebrada de Humahuaca. In that sense, the ruling said that what must be protected is “the fundamental human right to a healthy, uncontaminated environment, doing whatever is necessary” to secure it.

“It is an absurd contradiction to allow further exploitation, such as open-pit mining, in a reserve declared a World Cultural and Natural Heritage of Humanity site” by UNESCO, it said. The court also warned that the title of World Heritage of Humanity “can be revoked” and if that happened “it would surely damage the tourism infrastructure now in place” in the Quebrada de Humahuaca, a deep, narrow ravine between peaks of the Andes.

Uranios del Sur is a subsidiary of Switzerland-based Uranio AG, the majority shareholder of Canadian mining company Rome Resources Ltd., according to the suit brought by environmentalists and local inhabitants.

Sources: Latin America Herald Tribune, 24 April 2010; WISE Uranium at: www.wise-uranium.org
Contact: WISE Argentina

About: 
Wise Uranium